Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Angul)
|
EDS
|
User Agency (bbsriocexpansion@gmail.com)
|
21/05/2022
|
3354 dt. 20.05.2022
|
|
2
|
User Agency (bbsriocexpansion@gmail.com)
|
REPLY
|
DFO (Angul)
|
27/09/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Angul)
|
04/11/2022
|
Please comply the EDS vide this office Memo No.22330 dated 03.11.2022
|
|
4
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
05/11/2022
|
DFO Angul to Comply the observation made by PCCF, Odisha
|
|
5
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
09/01/2023
|
Memo No.9421 dt.26.12.2022
|
|
6
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
18/01/2023
|
Compliance alongwith diversion proposal for 20.383 ha of Bhubaneswari OCP.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Angul)
|
01/02/2023
|
Please comply the EDS vide this office Memo No. 1616 dated 31.01.2023
|
|
8
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
03/03/2023
|
Point wise compliance on the observation made by Pccf Nodal forwarded
|
|
9
|
Head Office
|
EDS
|
State secretary
|
05/07/2023
|
EDS
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
19/07/2023
|
For submission of necessary compliance
|
|
11
|
Nodal Officer
|
EDS
|
CF (Angul)
|
02/08/2023
|
Please comply the EDS vide this office Memo No. 15419 dated 01.08.2023
|
|
12
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
05/08/2023
|
DFO Angul to submit compliance
|
|
13
|
DFO (Angul)
|
EDS
|
User Agency (bbsriocexpansion@gmail.com)
|
17/08/2023
|
Memo 4586 dt. 05.08.2023
|
|
14
|
User Agency (bbsriocexpansion@gmail.com)
|
REPLY
|
DFO (Angul)
|
19/02/2024
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
19/02/2024
|
EDS reply
|
|
16
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
23/02/2024
|
DFO Angul to comply the observation and resubmission.
|
|
17
|
Nodal Officer
|
EDS
|
CF (Angul)
|
26/02/2024
|
Compliance sent to Nodal Officer wrongly by RCCF, Angul
|
|
18
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
26/02/2024
|
DFO Angul to comply the observation and resubmission.
|
|
19
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
05/04/2024
|
EDS reply
|
|
20
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
06/04/2024
|
DFO Angul need to be uploaded the revised CA Scheme
|
|
21
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
06/04/2024
|
EDS reply
|
|
22
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
06/04/2024
|
Point wise Compliance on the EDS raised by Govt. of India, MoEF & CC is forwarded
|
|
23
|
Nodal Officer
|
EDS
|
CF (Angul)
|
07/05/2024
|
Please comply the EDS vide this office Memo No. 9623 dated 07.05.2024.
|
|
24
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
08/05/2024
|
DFO Angul to submit required compliance/documents.
|
|
25
|
DFO (Angul)
|
EDS
|
User Agency (bbsriocexpansion@gmail.com)
|
10/05/2024
|
EDS to UA as per obervation made by the PCCF, Nodal.
|
|
26
|
User Agency (bbsriocexpansion@gmail.com)
|
REPLY
|
DFO (Angul)
|
16/05/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Angul)
|
EDS
|
User Agency (bbsriocexpansion@gmail.com)
|
03/06/2024
|
Reply to EDS dtd 07.05.2024 of CCF Nodal submitted vide Letter no 4123 dtd 03.06.2024 of DFO Angul
|
|
28
|
User Agency (bbsriocexpansion@gmail.com)
|
REPLY
|
DFO (Angul)
|
03/06/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
03/06/2024
|
Reply to EDS dtd 07.05.2024 of CCF Nodal submitted vide Letter no 4123 dtd 03.06.2024 of DFO Angul
|
|
30
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
11/06/2024
|
DFO Angul to submit compliance
|
|
31
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
15/06/2024
|
EDS reply
|
|
32
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
18/06/2024
|
Compliance on the observation made by PCCF(N) submitted.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
15/07/2024
|
The compliance to GoI observation dated 04.07.2023 is furnished.
|
|
34
|
State secretary
|
REPLY
|
Head Office
|
15/07/2024
|
Compliance furnished by PCCF (FD&NO, FCA), O/o the PCCF & HoFF, Odisha vide letter dtd.12.07.2024.
|
|