TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/149499/2021              (ii). Name of Project for which Forest Land is required : Laserda_Pacheri Manganese & Iron Block              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of forest land over 94.351 ha under Sec. under 2(ii) of F. C. Act, 1980 including 4.261 ha forest Safety Zone (3.858 ha along the ML boundary & 0.403 ha along the PWD road) within the granted LoI for Mining Lease over 131.800 ha.              (iv). File no. : 8-02/2023-FC              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 94.351
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/OR/MIN/149499/202122/11/202123/11/2021   23/11/2021   23/11/2021   23/11/2021 Keonjhar :23/11/2021Rourkela:
  24/02/2022 (Keonjhar)

Orissa:
23/03/2022
Orissa:
28/12/2022
07/01/202321/12/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 16/02/2023  
Replied by State Government (Orissa) on:03/06/2023  
Query raised by MoEFCC,New Delhi on 20/09/2023  
Replied by State Government (Orissa) on:20/11/2023  
Query raised by State Government (Orissa) on:15/03/2023  
Replied by Nodal Officer (Orissa) on:29/05/2023  
Query raised by State Government (Orissa) on:26/09/2023  
Replied by Nodal Officer (Orissa) on:18/11/2023  
Query raised by Nodal Officer (Orissa) on:05/04/2022  
Replied by Circle(Rourkela) on:19/11/2022  
Query raised by Nodal Officer (Orissa) on:22/03/2023  
Replied by Circle(Rourkela) on:18/05/2023  
Query raised by Nodal Officer (Orissa) on:25/05/2023  
Replied by Circle(Rourkela) on:29/05/2023  
Query raised by Nodal Officer (Orissa) on:27/10/2023  
Replied by Circle(Rourkela) on:13/11/2023  
Query raised by Circle (Rourkela) on:11/03/2022  
Replied by DFO (Keonjhar) on:21/03/2022  
Query raised by Circle (Rourkela) on:07/04/2022  
Replied by DFO (Keonjhar) on:17/11/2022  
Query raised by Circle (Rourkela) on:25/04/2023  
Replied by DFO (Keonjhar) on:16/05/2023  
Query raised by Circle (Rourkela) on:25/05/2023  
Replied by DFO (Keonjhar) on:27/05/2023  
Query raised by Circle (Rourkela) on:30/10/2023  
Replied by DFO (Keonjhar) on:09/11/2023  
Query raised by DFO (Keonjhar) on:27/11/2021  
Replied by UA on :13/01/2022  
Query raised by DFO (Keonjhar) on:15/03/2022  
Replied by UA on :15/03/2022  
Query raised by DFO (Keonjhar) on:11/04/2022  
Replied by UA on :10/06/2022  
Query raised by DFO (Keonjhar) on:20/09/2022  
Replied by UA on :21/10/2022  
Query raised by DFO (Keonjhar) on:26/04/2023  
Replied by UA on :30/04/2023  
Query raised by DFO (Keonjhar) on:30/10/2023  
Replied by UA on :31/10/2023  
NOTE:- Stage-I Approval accorded by : Head Office .