Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
07/02/2019
|
Compliance on deficiencies noticed in the submitted DRP.
|
|
2
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
14/03/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
02/04/2019
|
Please, submit the authenticated map of non-forest land allotted in village Podadihi with GPS reading & certificate by the Range Officer concerned as regards posting of Sign board, Pillars etc for preparation of CA Scheme.
|
|
4
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
08/05/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
22/05/2019
|
EDS
|
|
6
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
30/05/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
18/06/2019
|
Please, submit the diversion proposal showing 33 percentage of green belt area over 26.567 ha in the project area.
|
|
8
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
20/06/2019
|
The correction have been made as per the instruction received
|
|
9
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
12/07/2019
|
Please comply the EDS raised vide this office Memo No.1684 Dtd.12.07.2019
|
|
10
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
16/07/2019
|
EDS
|
|
11
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
23/07/2019
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
08/08/2019
|
Reply of EDS
|
|