TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/WATER/38906/2019              (ii). Name of Project for which Forest Land is required : Improvement of Water Supply in Bhedaghat district Jabalpur              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For drinking water supply Pipe line laid in Bhedaghat Required forest area 0.09 ha.              (iv). File no. : F-5/2019/10-11              (v). State : Madhya Pradesh              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.09
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MP/WATER/38906/201913/02/201909/05/2019  06/03/2019  01/03/2019  27/02/2019  21/02/2019  15/02/2019   20/05/2019  03/05/2019  02/03/2019  01/03/2019  23/02/2019  15/02/2019   20/05/2019   03/06/2019 Jabalpur(T) :04/06/2019Jabalpur(T):
  02/07/2020 (Jabalpur(T))

Madhya Pradesh:
09/07/2020
Madhya Pradesh:
20/07/2020
03/09/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Jabalpur(T)) on:19/06/2019  
Replied by UA on :19/06/2019  
NOTE:- Stage-I Approval accorded by : State Government .