TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/WATER/146338/2021              (ii). Name of Project for which Forest Land is required : construction of pipe water supply stand alone water supply scheme with installation of 5000 or 2x5000 liters polytghelene water storage tank at 5 meter high MS staging claming to provoide water throug              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : provoiding safe drinking water to the village through FHTC under Jal Jeevan mission Goverment scheme              (iv). File no. : F-5/2022/10-11/              (v). State : Madhya Pradesh              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.04824
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MP/WATER/146338/202124/08/202107/09/2021  27/08/2021  24/08/2021   09/09/2021  05/09/2021  25/08/2021   14/09/2021   08/12/2021 Vidisha(T) :09/12/2021Bhopal(T):
  10/12/2021 (Vidisha(T))

Madhya Pradesh:
30/12/2021
Madhya Pradesh:
06/01/2022
02/02/2022
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .