TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/ROAD/30035/2017              (ii). Name of Project for which Forest Land is required : Upgradation work of Ratlam Bajna Kushalgarh Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : R-62 0.113 H R-61 0.42 H R-67 1.852 H P-79 0.75 H for increased width of the road and for make a sufficient greadient              (iv). State : Madhya Pradesh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 3.376
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MP/ROAD/30035/201729/06/201929/11/2019  25/07/2019  18/07/2019  10/07/2019  29/06/2019   06/12/2019  26/07/2019  22/07/2019  18/07/2019  07/07/2019   27/07/2019   29/11/2019 Ratlam(T) :06/12/2019Ujjain(T):
  12/10/2021 (Ratlam(T))

Madhya Pradesh:
26/10/2021
Madhya Pradesh:
01/11/2021
Bhopal:
29/11/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhopal) on:08/01/2022  
Replied by State Government(Madhya Pradesh) on:03/02/2022  
Query raised by Regional Office (Bhopal) on:16/03/2022  
Replied by State Government(Madhya Pradesh) on:04/05/2022  
Query raised by Regional Office (Bhopal) on:25/08/2022  
Replied by State Government(Madhya Pradesh) on:08/12/2022  
Query raised by Regional Office (Bhopal) on:20/03/2023  
Replied by State Government(Madhya Pradesh) on:05/04/2023  
Query raised by Regional Office (Bhopal) on:25/05/2023  
Replied by State Government(Madhya Pradesh) on:30/05/2023  
Query raised by Regional Office (Bhopal) on:14/08/2023  
Query raised by State Government (Madhya Pradesh) on:21/04/2022  
Replied by Nodal Officer (Madhya Pradesh) on:04/05/2022  
Query raised by State Government (Madhya Pradesh) on:16/08/2023  
Query raised by Nodal Officer (Madhya Pradesh) on:21/04/2022  
Replied by Circle(Ujjain(T)) on:26/04/2022  
Query raised by Nodal Officer (Madhya Pradesh) on:04/05/2022  
Replied by Circle(Ujjain(T)) on:04/05/2022  
Query raised by Nodal Officer (Madhya Pradesh) on:16/08/2023  
Replied by Circle() on:  
Query raised by Circle (Ujjain(T)) on:21/04/2022  
Replied by DFO (Ratlam(T)) on:22/04/2022  
Query raised by Circle (Ujjain(T)) on:04/05/2022  
Replied by DFO (Ratlam(T)) on:04/05/2022  
Query raised by Circle (Ujjain(T)) on:16/08/2023  
Replied by DFO () on:  
Query raised by DFO (Ratlam(T)) on:12/12/2019  
Replied by UA on :28/01/2020  
Query raised by DFO (Ratlam(T)) on:11/02/2020  
Replied by UA on :05/10/2021  
Query raised by DFO (Ratlam(T)) on:08/10/2021  
Replied by UA on :08/10/2021  
Query raised by DFO (Ratlam(T)) on:11/10/2021  
Replied by UA on :11/10/2021  
Query raised by DFO (Ratlam(T)) on:21/04/2022  
Replied by UA on :22/04/2022  
Query raised by DFO (Ratlam(T)) on:04/05/2022  
Replied by UA on :04/05/2022  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .