Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dhar(T))
|
EDS
|
User Agency (dm-indore2@mp.gov.in)
|
31/05/2022
|
change area in part -1
|
|
2
|
User Agency (dm-indore2@mp.gov.in)
|
REPLY
|
DFO (Dhar(T))
|
01/06/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Dhar(T))
|
EDS
|
User Agency (dm-indore2@mp.gov.in)
|
01/06/2022
|
plz upload affected area 1.065 hac. in part I
|
|
4
|
User Agency (dm-indore2@mp.gov.in)
|
REPLY
|
DFO (Dhar(T))
|
01/06/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dhar(T))
|
EDS
|
User Agency (dm-indore2@mp.gov.in)
|
02/06/2022
|
plz read attached letter carefully
|
|
6
|
User Agency (dm-indore2@mp.gov.in)
|
REPLY
|
DFO (Dhar(T))
|
22/06/2022
|
The correction have been made as per the instruction received
|
|