  (i). Proposal No. : FP/MP/Pipeline/145254/2021              (ii). Name of Project for which Forest Land is required : Laying of water supply pipe line Under Tendukheda-Jabera Multi village rural water supply scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This scheme has been proposed in under RoW along with existing for the Laying of water supply pipeline 2000mX0.75m=0.1515 ha in Rani Durgawati Sanctuary Park and 2000mX0.70m=0.1400 ha in the Eco Sensitive Zone of Rani Durgawati Sanctuary Park Damoh total 0.2525 ha forest land              (iv). File no. : F-5              (v). State : Madhya Pradesh              (vi). Category of the Project : Pipeline              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.2525
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MP/Pipeline/145254/202128/07/2021aa02/08/2021   25/08/2021 Damoh(T) :27/08/2021Sagar(T):
  01/09/2021 (Damoh(T))

Madhya Pradesh:
07/09/2021
Madhya Pradesh:
18/11/2021
19/11/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .