TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/Others/27128/2017              (ii). Name of Project for which Forest Land is required : Establishment of Special Economic Zone, Chhindwara              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To develop special economic zone. This zone will facilitate various industries for production of multi product.              (iv). File no. : 8-16/2019-FC              (v). State : Madhya Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 80.737
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MP/Others/27128/201713/07/201704/08/2017  04/08/2017  02/08/2017  14/07/2017   24/08/2017  04/08/2017  03/08/2017  01/08/2017   29/08/2017   28/09/2017 Chhindwara South(T) :28/09/2017Chhindwara(T):
  11/03/2019 (Chhindwara South(T))

Madhya Pradesh:
12/03/2019
Madhya Pradesh:
02/04/2019
22/04/201911/02/2020
By :Head Office
Madhya Pradesh
14/03/2022
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 23/07/2019  
Replied by State Government (Madhya Pradesh) on:25/07/2019  
Query raised by State Government (Madhya Pradesh) on:22/04/2019  
Replied by Nodal Officer (Madhya Pradesh) on:22/04/2019  
Query raised by State Government (Madhya Pradesh) on:25/07/2019  
Replied by Nodal Officer (Madhya Pradesh) on:25/07/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:28/03/2019  
Replied by Circle(Chhindwara(T)) on:28/03/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:01/04/2019  
Replied by Circle(Chhindwara(T)) on:01/04/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:22/04/2019  
Replied by Circle(Chhindwara(T)) on:22/04/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:25/07/2019  
Replied by Circle(Chhindwara(T)) on:25/07/2019  
Query raised by Circle (Chhindwara(T)) on:28/03/2019  
Replied by DFO (Chhindwara South(T)) on:28/03/2019  
Query raised by Circle (Chhindwara(T)) on:01/04/2019  
Replied by DFO (Chhindwara South(T)) on:01/04/2019  
Query raised by Circle (Chhindwara(T)) on:22/04/2019  
Replied by DFO (Chhindwara South(T)) on:22/04/2019  
Query raised by Circle (Chhindwara(T)) on:25/07/2019  
Replied by DFO (Chhindwara South(T)) on:25/07/2019  
Query raised by DFO (Chhindwara South(T)) on:09/10/2017  
Replied by UA on :14/05/2018  
Query raised by DFO (Chhindwara South(T)) on:17/12/2018  
Replied by UA on :17/12/2018  
Query raised by DFO (Chhindwara South(T)) on:22/01/2019  
Replied by UA on :22/01/2019  
Query raised by DFO (Chhindwara South(T)) on:28/03/2019  
Replied by UA on :28/03/2019  
Query raised by DFO (Chhindwara South(T)) on:01/04/2019  
Replied by UA on :01/04/2019  
Query raised by DFO (Chhindwara South(T)) on:25/07/2019  
Replied by UA on :25/07/2019  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 30/03/2022  
Replied by State Government (Madhya Pradesh) on:10/05/2022  
Query raised by MoEFCC,New Delhi 24/05/2022  
NOTE:- Proposal is pending at State Government for verifying Compliance of Conditions due to EDS raised by HO for Stage-II .