Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Bhopal(T))
|
EDS
|
DFO (Obedullahganj(T))
|
22/02/2020
|
GEO map and SOI map is mismatch
|
|
2
|
DFO (Obedullahganj(T))
|
EDS
|
User Agency (objbill@gmail.com)
|
24/02/2020
|
As per DFO letter no.489 dated 24.02.20
|
|
3
|
User Agency (objbill@gmail.com)
|
REPLY
|
DFO (Obedullahganj(T))
|
05/12/2020
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Obedullahganj(T))
|
REPLY
|
CF (Bhopal(T))
|
29/12/2020
|
Correction have been made.
|
|
5
|
DFO (Obedullahganj(T))
|
REPLY
|
CF (Bhopal(T))
|
29/12/2020
|
Correction have been made.
|
|
6
|
CF (Bhopal(T))
|
EDS
|
DFO (Obedullahganj(T))
|
30/12/2020
|
hard copy is not submitted
|
|
7
|
DFO (Obedullahganj(T))
|
REPLY
|
CF (Bhopal(T))
|
02/01/2021
|
hard copy of proposal is submitted
|
|