| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
08/04/2019
|
|
|
|
2
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
08/04/2019
|
|
|
|
3
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
08/04/2019
|
|
|
|
4
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
08/04/2019
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
08/04/2019
|
|
|
|
6
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
08/04/2019
|
|
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
30/05/2019
|
|
|
|
8
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
30/05/2019
|
|
|
|
9
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
30/05/2019
|
|
|
|
10
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
30/05/2019
|
|
|
|
11
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
30/05/2019
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
30/05/2019
|
|
|
|
13
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
30/05/2019
|
|
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
30/05/2019
|
|
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
21/06/2019
|
EDS on 21.06.2019
|
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2019
|
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
29/06/2019
|
Nodal officer letter dated 28/06/2019 enclosed.
|
|
|
18
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
29/06/2019
|
Nodal officer letter dated 28/06/2019 enclosed.
|
|
|
19
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
29/06/2019
|
Nodal officer letter dated 28/06/2019 enclosed.
|
|
|
20
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
19/03/2020
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
20/03/2020
|
|
|
|
22
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
20/03/2020
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
20/03/2020
|
|
|
|
24
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
20/03/2020
|
|
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
20/03/2020
|
|
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
20/03/2020
|
Nodal officer letter dated 20/03/2020 enclosed.
|
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
25/04/2020
|
EDS
|
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
05/06/2020
|
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
05/06/2020
|
|
|
|
30
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
05/06/2020
|
|
|
|
31
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
22/12/2020
|
|
|
|
32
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
16/01/2021
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
25/01/2021
|
Trees have been recalculated
|
|
|
34
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
05/02/2021
|
conting of tree list
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
09/02/2021
|
Nodal officer letter dated 09/02/2021 enclosed.
|
|
|
36
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
10/02/2021
|
ca sceam
|
|
|
37
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
15/01/2023
|
|
|
|
38
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
29/08/2023
|
The correction have been made as per the instruction received
|
|
|
39
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
29/08/2023
|
|
|
|
40
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
29/08/2023
|
|
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
29/08/2023
|
|
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
29/08/2023
|
nodal officer letter dated 28/08/2023 enclosed
|
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
28/12/2023
|
EDS letter on 28.12.2023
|
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
24/01/2024
|
|
|
|
45
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
24/01/2024
|
Nodal officer letter dated 24/01/2024 enclosed.
|
|
|
46
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
24/01/2024
|
Nodal officer letter dated 24/01/2024 enclosed.
|
|
|
47
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
18/03/2025
|
|
|
|
48
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
18/03/2025
|
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
18/03/2025
|
Nodal officer letter dated 02/01/2025 enclosed.
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
18/03/2025
|
Nodal officer letter dated 02/01/2025 enclosed.
|
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
21/03/2025
|
EDS
|
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
21/03/2025
|
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
21/03/2025
|
Nodal officer letter dated 21/03/2025 enclosed.
|
|
|
54
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
21/03/2025
|
Nodal officer letter dated 21/03/2025 enclosed.
|
|
|
55
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
07/07/2025
|
Change the KML File From Part-1
|
|
|
56
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
10/07/2025
|
The correction have been made as per the instruction received
|
|
|
57
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
10/07/2025
|
???? ????? ???????? ?? ??? ?????? ???????? ???????? ?? ?????? ?????? ?? ?? ????????? ?? ?????? ????? ???????, ?? ????? ?????? ??? ?? ???????? ?????? ?? ?? ?? ??? ?????? ??? ???????? ?????? ?????? ????????? ???? ?? ???? ?????
|
|
|
58
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
17/07/2025
|
The 14 point information uploaded by you is not being displayed on the portal. Please correct it.
|
|
|
59
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
19/07/2025
|
The objections taken by the Ministry of Environment and Forests, Government of India have been fulfilled by the applicant institute and Divisional Forest Officer, Tikamgarh/Chhatarpur. Point wise information has been sent along with recommendations.
|
|
|
60
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
23/07/2025
|
The objection raisedhas been met by the dfo
|
|
|
61
|
Nodal Officer
|
REPLY
|
State secretary
|
24/07/2025
|
Nodal officer letter dated 24/09/2025 enclosed.
|
|
|
62
|
State secretary
|
REPLY
|
Regional Office
|
24/07/2025
|
Nodal officer letter dated 24/07/2025 enclosed.
|
|
|
63
|
Head Office
|
EDS
|
State secretary
|
25/08/2025
|
EDS
|
|
|
64
|
State secretary
|
EDS
|
Nodal Officer
|
01/09/2025
|
|
|
|
65
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
01/09/2025
|
Nodal officer letter dated 22/08/2025 enclosed.
|
|
|
66
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Tikamgarh(T))
|
01/09/2025
|
Nodal officer letter dated 22/08/2025 enclosed.
|
|
|
67
|
DFO (Tikamgarh(T))
|
EDS
|
User Agency (ap.singh.work@gmail.com)
|
01/09/2025
|
Nodal officer letter dated 22/08/2025 enclosed.
|
|
|
68
|
User Agency (ap.singh.work@gmail.com)
|
REPLY
|
DFO (Tikamgarh(T))
|
08/09/2025
|
The correction have been made as per the instruction received
|
|
|
69
|
DFO (Tikamgarh(T))
|
REPLY
|
CF (Chhatarpur(T))
|
08/09/2025
|
The Government of India has sought information about 03 points in the case by the Ministry of Environment Forest and Climate Change. Which has been fulfilled by the User Agency uploaded to the portal Part-1. Which sent for the active action including recommendation.
|
|
|
70
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
09/09/2025
|
03 points in the case have been uploaded on the portal part-1 by the user agency
|
|
|
71
|
Nodal Officer
|
REPLY
|
State secretary
|
09/09/2025
|
Nodal officer letter dated 09/09/2025 enclosed.
|
|
|
72
|
State secretary
|
REPLY
|
Head Office
|
09/09/2025
|
Nodal officer letter dated 09/09/2025 enclosed.
|
|