  (i). Proposal No. : FP/MP/MIN/123539/2021              (ii). Name of Project for which Forest Land is required : Vishnupuri UG to OC Mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 143.083 Ha forest land (4.452 Ha of RF 730 B, 54.331 of PF 730C, 24.276 of PF 719B and 60.024 Ha revenue forest) for Vishnupuri UG to OC coal mine of Pench Area, WCL.              (iv). State : Madhya Pradesh              (v). Category of the Project : Mining              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 135.008
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR)Stage-I Approval onStage-II Approval on
FP/MP/MIN/123539/202107/03/202214/03/2022   06/04/2022   07/04/2022   07/12/2022 Chhindwara West(T) :07/12/2022
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by DFO (Chhindwara West(T)) on:07/12/2022  
Replied by UA on :21/12/2022  
Query raised by DFO (Chhindwara West(T)) on:27/12/2022  
Replied by UA on :12/06/2023  
Query raised by DFO (Chhindwara West(T)) on:16/06/2023  
Replied by UA on :22/06/2023  
Query raised by DFO (Chhindwara West(T)) on:20/10/2023  
Replied by UA on :27/07/2024  
Query raised by DFO (Chhindwara West(T)) on:08/08/2024  
Replied by UA on :21/07/2025  
Query raised by DFO (Chhindwara West(T)) on:11/09/2025  
Replied by UA on :19/11/2025  
Query raised by DFO (Chhindwara West(T)) on:26/11/2025  
Replied by UA on :15/01/2026  
Query raised by DFO (Chhindwara West(T)) on:20/01/2026  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .