  (i). Proposal No. : FP/MP/MIN/10885/2015              (ii). Name of Project for which Forest Land is required : Jamunia Under Ground Mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 54.639 Ha.revenue forest land for under ground coal mining purpose.              (iv). File no. : 8-47/2017-FC              (v). State : Madhya Pradesh              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 54.639
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MP/MIN/10885/201515/03/201516/12/2016  07/12/2016  08/11/2016  06/09/2016  18/05/2015  26/03/2015   19/12/2016  09/12/2016  24/11/2016  01/11/2016  28/08/2016  09/05/2015   20/12/2016   04/02/2017 Chhindwara West(T) :04/02/2017Chhindwara(T):
  22/03/2017 (Chhindwara West(T))

Madhya Pradesh:
14/05/2017
Madhya Pradesh:
18/05/2017
13/06/201703/01/2018
By :Head Office
Madhya Pradesh
26/12/2020
05/01/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Circle (Chhindwara(T)) on:23/03/2017  
Replied by DFO (Chhindwara West(T)) on:02/05/2017  
Query raised by DFO (Chhindwara West(T)) on:21/02/2017  
Replied by UA on :02/03/2017  
Query raised by DFO (Chhindwara West(T)) on:24/03/2017  
Replied by UA on :19/04/2017  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 01/02/2021  
Replied by State Government (Madhya Pradesh) on:26/07/2023  
Query raised by MoEFCC,New Delhi 09/08/2023  
Replied by State Government (Madhya Pradesh) on:14/08/2023  
Query raised by MoEFCC,New Delhi 28/08/2023  
Replied by State Government (Madhya Pradesh) on:29/09/2023  
Query raised by MoEFCC,New Delhi 13/10/2023  
Replied by State Government (Madhya Pradesh) on:05/12/2023  
NOTE:- Stage-II Approval accorded by : Head Office .