TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/IRRIG/32224/2018              (ii). Name of Project for which Forest Land is required : Tendua Nalla Tank Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Tendua Nalla Tank schemes is proposed to irrigate 340 ha. Rabi crop. During last few years there has been drought seen in the region that makes the people scratchy of food grain. By introducing the new irrigation scheme in the region the people of the area will get sufficient food grain and emplo              (iv). File no. : 8-20/2019-FC              (v). State : Madhya Pradesh              (vi). Category of the Project : Irrigation              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 45.278
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MP/IRRIG/32224/201812/03/201816/05/2018  15/05/2018  14/05/2018  16/03/2018   21/05/2018  15/05/2018  14/05/2018  13/05/2018   21/05/2018   04/06/2018 Chhatarpur(T) :05/06/2018Chhatarpur(T):
  25/10/2018 (Chhatarpur(T))

Madhya Pradesh:
13/12/2018
Madhya Pradesh:
22/04/2019
29/05/201911/03/2020
By :Head Office
Madhya Pradesh
30/08/2022
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 25/07/2019  
Replied by State Government (Madhya Pradesh) on:31/12/2019  
Query raised by State Government (Madhya Pradesh) on:26/12/2019  
Replied by Nodal Officer (Madhya Pradesh) on:30/12/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:05/01/2019  
Replied by Circle(Chhatarpur(T)) on:22/04/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:26/12/2019  
Replied by Circle(Chhatarpur(T)) on:30/12/2019  
Query raised by Circle (Chhatarpur(T)) on:25/10/2018  
Replied by DFO (Chhatarpur(T)) on:25/10/2018  
Query raised by Circle (Chhatarpur(T)) on:09/11/2018  
Replied by DFO (Chhatarpur(T)) on:07/12/2018  
Query raised by Circle (Chhatarpur(T)) on:10/01/2019  
Replied by DFO (Chhatarpur(T)) on:22/04/2019  
Query raised by Circle (Chhatarpur(T)) on:26/12/2019  
Replied by DFO (Chhatarpur(T)) on:30/12/2019  
Query raised by DFO (Chhatarpur(T)) on:26/12/2019  
Replied by UA on :28/12/2019  
Query raised by DFO (Chhatarpur(T)) on:28/12/2019  
Replied by UA on :28/12/2019  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 09/09/2022  
NOTE:- Proposal is pending at State Government for verifying Compliance of Conditions due to EDS raised by HO for Stage-II .