Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (North Shahdol(T))
|
EDS
|
User Agency (eewrd.shahdol130@gmail.com)
|
16/10/2017
|
the agency has been not submitted the hard copy of there online application is office of the dfo it has been ask to do the shem by the letter no. 1670 date 16.10.2017
|
|
2
|
User Agency (eewrd.shahdol130@gmail.com)
|
REPLY
|
DFO (North Shahdol(T))
|
16/11/2017
|
The correction have been made as per the instruction received
|
|
3
|
DFO (North Shahdol(T))
|
EDS
|
User Agency (eewrd.shahdol130@gmail.com)
|
23/11/2017
|
agency has not submitted the hard copy of all documents as the check list. it has been ask do the same by letter no. 1841 date 22.11.2017
|
|
4
|
User Agency (eewrd.shahdol130@gmail.com)
|
REPLY
|
DFO (North Shahdol(T))
|
06/12/2017
|
The correction have been made as per the instruction received
|
|
5
|
DFO (North Shahdol(T))
|
EDS
|
User Agency (eewrd.shahdol130@gmail.com)
|
02/01/2018
|
the user agency has not deposited registration and processing fee it has been asked by letter no. 03 date 02-01-2018
|
|
6
|
User Agency (eewrd.shahdol130@gmail.com)
|
REPLY
|
DFO (North Shahdol(T))
|
10/01/2018
|
The correction have been made as per the instruction received
|
|
7
|
CF (Shahdol(T))
|
EDS
|
DFO (North Shahdol(T))
|
11/03/2018
|
for correction
|
|
8
|
DFO (North Shahdol(T))
|
REPLY
|
CF (Shahdol(T))
|
11/03/2018
|
after correction
|
|
9
|
CF (Shahdol(T))
|
EDS
|
DFO (North Shahdol(T))
|
11/03/2018
|
please upload site inspection report
|
|
10
|
DFO (North Shahdol(T))
|
REPLY
|
CF (Shahdol(T))
|
11/03/2018
|
after correction
|
|
11
|
Nodal Officer
|
EDS
|
CF (Shahdol(T))
|
22/03/2018
|
Nodal officer letter dated 22-03-2018 enclosed
|
|
12
|
CF (Shahdol(T))
|
EDS
|
DFO (North Shahdol(T))
|
02/04/2018
|
Letter attached
|
|
13
|
DFO (North Shahdol(T))
|
EDS
|
User Agency (eewrd.shahdol130@gmail.com)
|
09/04/2018
|
The agencies has not submitted hard copy of all documents as the check list it has been asked do the shem by latter no. 509 date 28-03-2018
|
|
14
|
User Agency (eewrd.shahdol130@gmail.com)
|
REPLY
|
DFO (North Shahdol(T))
|
02/05/2018
|
The correction have been made as per the instruction received
|
|
15
|
DFO (North Shahdol(T))
|
REPLY
|
CF (Shahdol(T))
|
26/05/2018
|
correction latter
|
|
16
|
CF (Shahdol(T))
|
REPLY
|
Nodal Officer
|
27/05/2018
|
letter attached
|
|