TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MN/WATER/120050/2021              (ii). Name of Project for which Forest Land is required : Construction of Water Supply Scheme at Lamlongei, Koirengei Cluster              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Without the Forest land, the Water Reservoir cannot attain the required height for efficient distribution of water.              (iv). File no. : 20/42/2021-For&Envt              (v). State : Manipur              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.37
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MN/WATER/120050/202119/01/2021aa21/01/2021   29/01/2021 Central Forest Division,Imphal :29/01/2021Central Forest Circle:
  08/03/2021 (Central Forest Division,Imphal)

Manipur:
12/03/2021
Manipur:
26/04/2021
28/04/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Central Forest Division,Imphal) on:06/02/2021  
Replied by UA on :08/03/2021  
NOTE:- Stage-I Approval accorded by : State Government .