Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Western Forest Division,Tamenglong)
|
EDS
|
User Agency (md.mspcl@gmail.com)
|
16/07/2019
|
The area stated in the Addl. NPV undertaking is not correct. Therefore, it is requested to upload the corrected copy of the Addl. NPV undertaking.
|
|
2
|
User Agency (md.mspcl@gmail.com)
|
REPLY
|
DFO (Western Forest Division,Tamenglong)
|
12/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
08/04/2021
|
Please do correction on the SIR
|
|
4
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
08/04/2021
|
Proposed Diversion of forest land over 1.831 ha for “Construction of 132/33 KV Tamenglong Sub-Station” under NERPSIP with World Bank funding to be taken up by MSPCL.
The project involved minimum tree felling and no significant adverse impact on the existing eco-system is anticipated. The proposed area is the barest minimum and for public utility. Therefore, considering the importance of the project in developing a reliable and uninterrupted power supply in the region for overall development of the district, the project is recommended for consideration.
Hence, the proposal is recommended for clearance under section 2 of the Forest (Conservation) Act, 1980.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
20/04/2021
|
3 sets of original/coloured scanned copies to be submitted at an earliest for further processing
|
|
6
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
28/04/2021
|
3 sets of original/coloured scanned copies to be submitted at an earliest for further processing
|
|
7
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
15/06/2021
|
required information submitted
|
|
8
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
18/06/2021
|
Details Submitted
|
|