TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MN/TRANS/36731/2018              (ii). Name of Project for which Forest Land is required : Construction of 132 KV single circuit transmission line on double circuit towers from Rengpang to Tamenglong under North Eastern Region Power System Improvement Project (NERPSIP)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Project for the construction of 132 kv transmission line from Rengpang to Tamenglong is a part of establishing 132/33 kv transmission system in Tamenglong District Headquarter in order to develop robust grid infrastructure to give a reliable and uninterrupted power supply system in Tamenglong Di              (iv). File no. : 3-MN C 105/2019-SHI              (v). State : Manipur              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 56.833
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MN/TRANS/36731/201825/10/201827/10/2018   30/10/2018   03/11/2018   12/11/2018 Western Forest Division,Tamenglong :13/11/2018Western Forest Circle:
  27/05/2019 (Western Forest Division,Tamenglong)

Manipur:
15/06/2019
Manipur:
20/04/2021
Shillong:
20/04/2021
30/01/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Western Forest Division,Tamenglong) on:27/03/2019  
Replied by UA on :04/04/2019  
NOTE:- Stage-I Approval accorded by : Regional Office .