Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Eastern Forest Circle)
|
25/01/2016
|
The proposal submitted is in- complete. The information on i. Detailed calculation sheet of NPV, ii. Undertaking for payment of NPV & addl. NPV from UA, iii. Certificate from DC, Chandel for Non-availability of non-forest land for CA may be submitted.
|
|
2
|
CF (Eastern Forest Circle)
|
EDS
|
DFO (Tengnoupal Forest Division, Chandel)
|
25/01/2016
|
The proposal submitted is in- complete. The information on i. Detailed calculation sheet of NPV, ii. Undertaking for payment of NPV & addl. NPV from UA, iii. Certificate from DC, Chandel for Non-availability of non-forest land for CA may be submitted.
|
|
3
|
DFO (Tengnoupal Forest Division, Chandel)
|
REPLY
|
CF (Eastern Forest Circle)
|
25/01/2016
|
The information on (i) calculation of NPV (ii) undertaking for payment of NPV and addl. NPV from UA is provided here and the hard copies have also been sent. The DC Chandel has been requested to issue a certificate on "Non-availability of non-forest land" for compensatory afforestation in Chandel District and the same is awaited.
|
|
4
|
CF (Eastern Forest Circle)
|
REPLY
|
Nodal Officer
|
25/01/2016
|
The information sought is provided here for kind perusal and necessary action
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
27/01/2016
|
NPV may be verified once again
|
|
6
|
Nodal Officer
|
EDS
|
CF (Eastern Forest Circle)
|
27/01/2016
|
NPV may be verified once again
|
|
7
|
CF (Eastern Forest Circle)
|
REPLY
|
Nodal Officer
|
27/01/2016
|
Revised NPV submitted
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
27/01/2016
|
Revised NPV submitted
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
25/04/2016
|
Deficiency Observed
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
21/07/2016
|
Information sought vide letter F.No. 3 MN C 007/2016-SHI/250-52 dt. 22/04/2016 has been submitted.
|
|