Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Eastern Forest Circle)
|
EDS
|
DFO (Kamjong forest division)
|
25/07/2020
|
some documents still need to be uploaded
|
|
2
|
DFO (Kamjong forest division)
|
REPLY
|
CF (Eastern Forest Circle)
|
17/08/2020
|
All relevant documents (hard copies) are submitted for further necessary action
|
|
3
|
CF (Eastern Forest Circle)
|
EDS
|
DFO (Kamjong forest division)
|
21/08/2020
|
Some relevant and vital information are still wanting. DFO advised to meticulously fill the Form A Part-II and resubmit at the earliest for further processing
|
|
4
|
DFO (Kamjong forest division)
|
REPLY
|
CF (Eastern Forest Circle)
|
23/10/2020
|
Sir i am unable to upload the pdf & kml file due to unknown error.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Eastern Forest Circle)
|
20/04/2021
|
1. The scheme for raising Avenue Plantation, Existing and proposed RoW, details of the existing and proposed length of the road, details of Muck Disposal Plan, muck details, muck like to be generated to submitted by the User Agency after duly signed by the DFO
|
|