TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MN/ROAD/34066/2018              (ii). Name of Project for which Forest Land is required : Widening and improvement of Yaingangpokpi-Nagaland Road Section of NH-202 into two laning with paved shoulder of 0.000km from Laikot to Hungpung of 48.273 km in the State of Manipur on EPC Mode by NHIDCL              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed project road is located in three districts namely: Imphal East, Kamjong, Kangpokpi and Ukhrul. The project corridor takes off from Laikot near Yaingangpokpi to Hungpung. This road has an approximate length of 43.129 km from Laikot at existing chainage of 0.000 km of NH-202 to 48.273 km              (iv). File no. : 3-MN A 043/2020-SHI              (v). State : Manipur              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 149.708
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MN/ROAD/34066/201807/06/2018aa08/06/2018   21/06/2018 Central Forest Division,Imphal:  29/06/2018
Eastern Forest Division,Ukhrul:  29/06/2018
Thoubal Forest Division:  29/06/2018
Eastern Forest Circle:
  15/04/2019 (Eastern Forest Division,Ukhrul)

Central Forest Circle:
  19/08/2019 (Thoubal Forest Division)

Central Forest Circle:
  03/09/2019 (Central Forest Division,Imphal)

Manipur:
26/11/2019
Manipur:
01/12/2020
Shillong:
08/12/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:09/12/2020  
Replied by State Government(Manipur) on:20/01/2021  
Query raised by Regional Office (Shillong) on:19/04/2021  
Query raised by Nodal Officer (Manipur) on:29/11/2019  
Replied by Circle(Central Forest Circle) on:01/12/2020  
Query raised by DFO (Eastern Forest Division,Ukhrul) on:17/01/2019  
Replied by UA on :03/03/2019  
Query raised by DFO (Eastern Forest Division,Ukhrul) on:15/04/2019  
Replied by UA on :24/04/2019  
Query raised by DFO (Eastern Forest Division,Ukhrul) on:13/06/2019  
Replied by UA on :13/06/2019  
Query raised by DFO (Eastern Forest Division,Ukhrul) on:20/06/2019  
Replied by UA on :20/06/2019  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .