| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Western Forest Division,Tamenglong)
|
EDS
|
User Agency (nhidclimphal@gmail.com)
|
24/09/2016
|
the following details are required for processing at division
1. Toposheet map clearly indicating the surrounding area
2. forest cover ,FSI, showing area statement, dense, open, scrub
3. division area statement of patches to be acquired by the UA
3. clearification of the total areaof the project
|
|
|
2
|
User Agency (nhidclimphal@gmail.com)
|
REPLY
|
DFO (Western Forest Division,Tamenglong)
|
19/10/2016
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Western Forest Division,Tamenglong)
|
EDS
|
User Agency (nhidclimphal@gmail.com)
|
21/10/2016
|
Total area given in the georeference map showing diversion of 3.73 ha of forest land for construction of Superstructure bridge over river Barak does not commensurate wit the areas of M.Dense Forest, Open Forest, Water Bodies and scrubs. Please recheck and do necessary rectification if any.
|
|
|
4
|
User Agency (nhidclimphal@gmail.com)
|
REPLY
|
DFO (Western Forest Division,Tamenglong)
|
21/10/2016
|
The correction have been made as per the instruction received
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
04/11/2016
|
The following information may please be corrected/rectified, In Part-II 7vii the density of vegetation should be above 45 as it is mentioned that open to moderately dense forest included in the area for diversion. Correspondingly crown density in site inspection and calculation of NPV may be corrected.
|
|
|
6
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
05/11/2016
|
The following information may please be corrected/rectified, In Part-II 7vii the density of vegetation should be above 45 as it is mentioned that open to moderately dense forest included in the area for diversion. Correspondingly crown density in site inspection and calculation of NPV may be corrected.
|
|
|
7
|
CF (Western Forest Circle)
|
EDS
|
DFO (Jiribam Forest Division,Jiribtun)
|
05/11/2016
|
The following information may please be corrected/rectified, In Part-II 7vii the density of vegetation should be above 45 as it is mentioned that open to moderately dense forest included in the area for diversion. Correspondingly crown density in site inspection and calculation of NPV may be corrected.
|
|
|
8
|
DFO (Jiribam Forest Division,Jiribtun)
|
EDS
|
User Agency (nhidclimphal@gmail.com)
|
05/11/2016
|
All necessary documents have been checked and made rectified.
|
|
|
9
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
05/11/2016
|
All necessary documents have been checked and rectified.
|
|
|
10
|
User Agency (nhidclimphal@gmail.com)
|
REPLY
|
DFO (Jiribam Forest Division,Jiribtun)
|
05/11/2016
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Jiribam Forest Division,Jiribtun)
|
REPLY
|
CF (Western Forest Circle)
|
05/11/2016
|
All documents have been rechecked and rectified.
|
|
|
12
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
05/11/2016
|
All documents have been rechecked and rectified.
|
|