Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Northern Forest Circle)
|
EDS
|
DFO (Northern Forest Division,Ktuigpokpi)
|
30/04/2016
|
Name of the Density of forest to be modified as moderately dense forest instead of medium dense forest
Density of vegetation to be rectified
name of project works to be mentioned in the certificate of Non availability of Land for Compensatory Afforestation
Name of protected Forest to be rectified as Tairenpokpi-Tamenglong PF instead of Kangchup Leimakhong PF
Physical and Financial target for CA to be increased from 5 years to 10 years
|
|
2
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
30/04/2016
|
Name of the Density of forest to be modified as moderately dense forest instead of medium dense forest Density of vegetation to be rectified name of project works to be mentioned in the certificate of Non availability of Land for Compensatory Afforestation Name of protected Forest to be rectified as Tairenpokpi-Tamenglong PF instead of Kangchup Leimakhong PF Physical and Financial target for CA to be increased from 5 years to 10 years
|
|
3
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
01/05/2016
|
All data sought have been rectified accordingly.
|
|
4
|
DFO (Northern Forest Division,Ktuigpokpi)
|
REPLY
|
CF (Northern Forest Circle)
|
02/05/2016
|
All queries have been rectified accordingly
|
|
5
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
02/05/2016
|
Rectified and upload the FORM A Part-II.
|
|
6
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
02/05/2016
|
Rectified recommendation file (PART-II) is submitted herewith superseding previously submitted on dt. 26/03/2016
|
|
7
|
Nodal Officer
|
EDS
|
CF (Northern Forest Circle)
|
04/05/2016
|
A.The following details needed from CF, North-
Para 2- spelling of Ktuigpokpi to be corrected
Para 12 II, III, IV -Forest area diverted and stipulated CA area to be corrected.
B. Needed from CF, Western
Para 7- Actual no. of trees to be felled is to be mentioned.
Para 9 IV- Amount to be corrected with corresponding to Phy & Fin Target for CA.
Para 12 II&III -Project like Rly line, Loktak D/S Approach Rd., Tupul-Bishnupur Rd. to be included and the area of CA to be corrected accordingly.
NPV - Percentage of crown density for very dense forest should be more than 70 and the word medium to be replaced by moderately.
In Site Inspection of DFO, Western forest type, main vegetation, crown density etc to be mentioned.
Separate Site Inspection of CA by CF, Western with Geo-coordinate.
|
|
8
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
04/05/2016
|
A.The following details needed from CF, North-
Para 2- spelling of Ktuigpokpi to be corrected
Para 12 II, III, IV -Forest area diverted and stipulated CA area to be corrected.
B. Needed from CF, Western
Para 7- Actual no. of trees to be felled is to be mentioned.
Para 9 IV- Amount to be corrected with corresponding to Phy & Fin Target for CA.
Para 12 II&III -Project like Rly line, Loktak D/S Approach Rd., Tupul-Bishnupur Rd. to be included and the area of CA to be corrected accordingly.
NPV - Percentage of crown density for very dense forest should be more than 70 and the word medium to be replaced by moderately.
In Site Inspection of DFO, Western forest type, main vegetation, crown density etc to be mentioned.
Separate Site Inspection of CA by CF, Western with Geo-coordinate.
|
|
9
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
05/05/2016
|
B. Needed from CF, Western Para 7- Actual no. of trees to be felled is to be mentioned. Para 9 IV- Amount to be corrected with corresponding to Phy & Fin Target for CA. Para 12 II&III -Project like Rly line, Loktak D/S Approach Rd., Tupul-Bishnupur Rd. to be included and the area of CA to be corrected accordingly. NPV - Percentage of crown density for very dense forest should be more than 70 and the word medium to be replaced by moderately. In Site Inspection of DFO, Western forest type, main vegetation, crown density etc to be mentioned.
|
|
10
|
CF (Northern Forest Circle)
|
REPLY
|
Nodal Officer
|
05/05/2016
|
Spelling of Ktuigpokpi cound not be corrected from our side it may please be corrected from NIC
Forest area diverted and stipulated CA area to be corrected, copy enclosed
|
|
11
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
09/05/2016
|
Corrected copy of the details sought from your end received on 05/05/2006
|
|
12
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
09/05/2016
|
All correction regarding no. of trees to be felled, amount corresponding to Phy. & Fin Target for CA, inclusion of stage I and stage 2 clear projects, CA area, NPV, forest type, main vegetation, crown density etc have been given along with Site inspection of CA by CF Western Circle at Langkhong along with geo-coordinate.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Northern Forest Circle)
|
10/05/2016
|
A.The following details need from CF North-
1. para 10 IV in the corrected page the amount of CA need to be corrected corresponding to CA Scheme.
B. From CF, Western-
1. Photograph of site inspection of CA by CF, Western may be corrected with GPS location.
2. Site Inspection report of CA site by CF, Western may be uploaded as additional information.
|
|
14
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
10/05/2016
|
A.The following details need from CF North-
1. para 10 IV in the corrected page the amount of CA need to be corrected corresponding to CA Scheme.
B. From CF, Western-
1. Photograph of site inspection of CA by CF, Western may be corrected with GPS location.
2. Site Inspection report of CA site by CF, Western may be uploaded as additional information.
|
|
15
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
11/05/2016
|
rectified copy of corrected GPS location along with inspection report for CA site are attached herewith.
|
|
16
|
CF (Northern Forest Circle)
|
REPLY
|
Nodal Officer
|
11/05/2016
|
para 10 (iv) total financial outlay for compensatory afforestation scheme has been corrected as Rs. 23.078 lakhs
|
|
17
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
12/05/2016
|
Check and verify the CA area noted under para 12 III in FORM Part III and also details of Enumeration of trees
|
|
18
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
13/05/2016
|
Check and verify the CA area noted under para 12 III in FORM Part III and also details of Enumeration of trees
|
|
19
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
13/05/2016
|
All correction regarding CA under para 12 (iii) and annexure-1 "Girth class wise enumeration of trees" have been made and entered successfully.
|
|
20
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
13/05/2016
|
All necessary rectification made by DFO, WFD have been check and forwarded for further action.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
25/05/2016
|
There is a discrepancy in between the no. of trees enumerated by User Agency and no. of trees enumerated by DFO, Western F/Divn. so, please check and verify the enumerated figure. If necessary please conduct a joint enumeration/verification consisting of the responsible representative of the User Agency.
|
|
22
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
01/06/2016
|
There is a discrepancy in between the no. of trees enumerated by User Agency and no. of trees enumerated by DFO, Western F/Divn. so, please check and verify the enumerated figure. If necessary please conduct a joint enumeration/verification consisting of the responsible representative of the User Agency.
|
|
23
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
20/06/2016
|
Discrepancy have been rectified after thorough consultation and coming into understanding between all the parties involved.
|
|
24
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
20/06/2016
|
All discrepancy with the no. of trees enumerated by User Agency and DFO, Western Forest Division have been found rectified and the same is acknowledge by CF, Western Circle for further n/action pls.
|
|
25
|
Nodal Officer
|
EDS
|
CF (Western Forest Circle)
|
21/06/2016
|
Please upload the rectified/corrected PDF file of the no. of trees enumerated jointly and signed by the User Agency and DFO/Western Forest Divn.
|
|
26
|
CF (Western Forest Circle)
|
EDS
|
DFO (Western Forest Division,Tamenglong)
|
21/06/2016
|
Please upload the rectified/corrected PDF file of the no. of trees enumerated jointly and signed by the User Agency and DFO/Western Forest Divn.
|
|
27
|
DFO (Western Forest Division,Tamenglong)
|
REPLY
|
CF (Western Forest Circle)
|
21/06/2016
|
The needed information has been uploaded as PDF file.
|
|
28
|
CF (Western Forest Circle)
|
REPLY
|
Nodal Officer
|
21/06/2016
|
The details of Enumeration of trees has been uploaded.
|
|