TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MN/QRY/44562/2020              (ii). Name of Project for which Forest Land is required : SANDSTONE/ROAD METAL, MURUM AND SHALY EARTH QUARRY              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : There are many developmental projects targeted to be implemented in the local demand of road, railway-line fitting as well as to supply to the various government, semi-government and private agencies for the construction of civil works, in play-ground filling, embankments for roads, flood banks, mar              (iv). File no. : 3-MNC 037/2021-SHI              (v). State : Manipur              (vi). Category of the Project : Quarrying              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 5.345
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MN/QRY/44562/202013/02/2020aa17/02/2020   21/02/2020 Noney forest division :28/04/2020Western Forest Circle:
  13/07/2020 (Noney forest division)

Manipur:
04/09/2020
Manipur:
28/06/2021
Shillong:
08/07/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:13/07/2021  
Replied by State Government(Manipur) on:28/10/2021  
Query raised by Regional Office (Shillong) on:20/12/2021  
Replied by State Government(Manipur) on:30/12/2021  
Query raised by Regional Office (Shillong) on:17/02/2022  
Replied by State Government(Manipur) on:20/05/2022  
Query raised by Regional Office (Shillong) on:05/12/2022  
Replied by State Government(Manipur) on:24/04/2023  
Query raised by Regional Office (Shillong) on:26/07/2023  
Query raised by State Government (Manipur) on:05/10/2021  
Replied by Nodal Officer (Manipur) on:28/10/2021  
Query raised by State Government (Manipur) on:30/12/2021  
Replied by Nodal Officer (Manipur) on:30/12/2021  
Query raised by State Government (Manipur) on:26/03/2022  
Replied by Nodal Officer (Manipur) on:20/05/2022  
Query raised by State Government (Manipur) on:24/04/2023  
Replied by Nodal Officer (Manipur) on:24/04/2023  
Query raised by Circle (Western Forest Circle) on:29/07/2020  
Replied by DFO (Noney forest division) on:20/08/2020  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .