Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Eastern Forest Circle)
|
EDS
|
DFO (Eastern Forest Division,Ukhrul)
|
28/08/2017
|
UA proposed the project for 30 years. Why DFO recommended for 100 years. It needs to be correction for 30 years as done by UA
|
|
2
|
DFO (Eastern Forest Division,Ukhrul)
|
EDS
|
User Agency (dcimanipur2017@gmail.com)
|
06/09/2017
|
In Form-A, Part-1, A-3,i copy of documents in support of the competence/authority of the person making this application to make application on behalf of the user agency is not submitted. Kindly submit the required document along with the photocopy of the ID card of the authorised signatory.
|
|
3
|
User Agency (dcimanipur2017@gmail.com)
|
REPLY
|
DFO (Eastern Forest Division,Ukhrul)
|
19/09/2017
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Eastern Forest Division,Ukhrul)
|
REPLY
|
CF (Eastern Forest Circle)
|
19/09/2017
|
there is no site for changing the year
|
|