TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/ML/TRANS/6093/2014              (ii). Name of Project for which Forest Land is required : Diversion of 11.04 ha of forest land for re-routing of a portion of existing 400 KV D/C Palatana- Bongaigaon Transmission line passing over RIST campus under Khasi Hills Forest Division, Meghalaya              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Enclosed in additional information section as Short narrative in serial no 6              (iv). State : Meghalaya              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 11.04
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/ML/TRANS/6093/201402/09/201430/10/2014   23/03/2015   23/03/2015   23/03/2015   Khasi Hills :23/03/2015Khasi&Jaintia Hills:
  06/05/2015 (Khasi Hills)

Meghalaya:
16/05/2015
Meghalaya:
21/05/2015
Shillong:
26/05/2015
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:16/08/2016  
Replied by State Government(Meghalaya) on:31/07/2018  
Query raised by Regional Office (Shillong) on:30/01/2020  
Query raised by Nodal Officer (Meghalaya) on:20/05/2015  
Replied by Circle(Khasi&Jaintia Hills) on:20/05/2015  
Query raised by Circle (Khasi&Jaintia Hills) on:20/05/2015  
Replied by DFO (Khasi Hills) on:20/05/2015  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .