Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jaintia Hills)
|
EDS
|
User Agency (goldstone.project@gmail.com)
|
26/05/2016
|
Sir,
There is a problem on uploading of the inspection report and image, where as the recommendation report could be uploaded, the matter may be from the technical point of view,hence time period is exhausted from this end and showing pending level at this office
|
|
2
|
User Agency (goldstone.project@gmail.com)
|
REPLY
|
DFO (Jaintia Hills)
|
23/08/2016
|
The correction have been made as per the instruction received
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
03/02/2017
|
1. Suitability Certificate from the DFO that the land identified for CA is suitable for raising plantation.
2. Certificate under the FRA 2006 as per the MoEF&CC Guidelines F.No.11-9/98-FC Pt. dated 5th July, 2013.
3. Undertaking to pay the additional NPV.
|
|
4
|
Nodal Officer
|
EDS
|
CF (Khasi&Jaintia Hills)
|
06/02/2017
|
EDS by State Govt to be replied by the DFO T Jowai-1. Suitability Certificate from the DFO that the land identified for CA is suitable for raising plantation. 2. Certificate under the FRA 2006 as per the MoEF&CC Guidelines F.No.11-9/98-FC Pt. dated 5th July, 2013. 3. Undertaking to pay the additional NPV. Please take immediate necessary action.
|
|
5
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
06/02/2017
|
EDS by State Govt to be replied by the DFO T Jowai for submission of 1. Suitability Certificate from the DFO that the land identified for CA is suitable for raising plantation. 2. Certificate under the FRA 2006 as per the MoEF&CC Guidelines F.No.11-9/98-FC Pt. dated 5th July, 2013. 3. Undertaking to pay the additional NPV. Please take immediate necessary action.
|
|
6
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
07/03/2017
|
Sir, matter has been complied vide this office Letter No.JH/GS/2017-18/396/A/810, dtd 7.03.2017
|
|
7
|
CF (Khasi&Jaintia Hills)
|
REPLY
|
Nodal Officer
|
14/03/2017
|
the DFO replied that matter has been complied vide his office Letter No.JH/GS/2017-18/396/A/810, dtd 7.03.2017
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
20/03/2017
|
Reply to query from Govt vide No. FOR.12/2017/178 dated 1.2.2017 already furnished vide this office letter No. MFG.16/50/Goldstone/4.578/17419 dated 17.3.2017 copy as attached PDF document titled 'EDS on GCL'.
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
08/05/2017
|
Additional information/ documents found lacking
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
31/05/2022
|
additional information pertaining to proposal as submitted by DFO jaintia Hills Division has been submitted vide letter dated 15th Sepmber, 2012
|
|