Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Khasi&Jaintia Hills)
|
17/06/2015
|
The Site Inspection Report of DFO as well as CF mention the area of forest as 4.86 ha in place of 4.869 ha in Part-I. Please clarify.
|
|
2
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
17/06/2015
|
The Site Inspection Report of DFO as well as CF mention the area of forest as 4.86 ha in place of 4.869 ha in Part-I. Please clarify.
|
|
3
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
24/06/2015
|
The area was mistakably mentioned as 4.86 ha instead of 4.869 ha, kindly note that the actual area as proposed by the user agency is 4.869 ha for any further reference
|
|
4
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
24/06/2015
|
The area was mistakably mentioned as 4.86 ha instead of 4.869 ha, kindly note that the actual area as proposed by the user agency is 4.869 ha for future reference
|
|
5
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
24/06/2015
|
Please correct the area in the recommendation letter also. Is should read as 4.869.
|
|
6
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
24/06/2015
|
The area recommended as proposed by the User Agency (NHAI)may pleased be read as 4.869 ha instead of 4.86 for future reference
|
|
7
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
24/06/2015
|
please upload in the Upload Recommendation option
|
|
8
|
DFO (Jaintia Hills)
|
EDS
|
User Agency (piushillong@nhai.org)
|
24/06/2015
|
The area recommended for diversion is as proposed by the user agency ie 4.869 ha
|
|
9
|
User Agency (piushillong@nhai.org)
|
REPLY
|
DFO (Jaintia Hills)
|
24/06/2015
|
the area proposed for recommendation is 4.869 ha
|
|
10
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
24/06/2015
|
uploading of recommendation report is not possible as the proposal did not appear in the list, hence recommendation report is uploaded in additional information of PART-II, the recommendation report is same (part of) as inspection report, thank you
|
|
11
|
CF (Khasi&Jaintia Hills)
|
REPLY
|
Nodal Officer
|
24/06/2015
|
Copies of the document uploaded in the EDS link may kindly be treated as updated as there is no option to remove the Recommendation link uploaded earlier for replacement.
|
|
12
|
Nodal Officer
|
EDS
|
CF (Khasi&Jaintia Hills)
|
25/06/2015
|
the period of recommendation is 10 year as per DFO report, since it is infrastructure project kindly clarify why it is not permanent
|
|
13
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
02/07/2015
|
Please refer the EDS of the Nodal Officer
|
|
14
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
02/07/2015
|
As the period for forest land diversion is mentioned as NIL by the User Agency, the initial recommendation period was given as 10 years.On re-examination, the period of recommendation is hereby corrected to 20 years
|
|
15
|
CF (Khasi&Jaintia Hills)
|
REPLY
|
Nodal Officer
|
03/07/2015
|
please refer the Clarifications made by the DFO.
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
21/08/2015
|
kindly send the certificate under the Forest Rights Act
|
|
17
|
Nodal Officer
|
EDS
|
CF (Khasi&Jaintia Hills)
|
27/08/2015
|
kindly send the certificate under the Forest Rights Act at the earliest.
|
|
18
|
CF (Khasi&Jaintia Hills)
|
REPLY
|
Nodal Officer
|
01/09/2015
|
The Certificate has been submitted by the UA.
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
02/09/2015
|
The Certificate under the Forest Rights Act has been received from the User Agency on 27.8.2015 and sent to Government on the same day.
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
07/09/2015
|
Kindly upload the FRA certificate online.
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
07/09/2015
|
The FRA certificate is enclosed herewith.
|
|
22
|
Regional Office
|
EDS
|
State secretary
|
10/12/2015
|
Additional Information ask
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
13/04/2016
|
Clearance from the NBWL awaited
|
|
24
|
Nodal Officer
|
EDS
|
CF (Khasi&Jaintia Hills)
|
14/04/2016
|
Wildlife clearance for the project from NBWL is desired by Govt.
|
|
25
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
15/04/2016
|
Please refer to the EDS raised by the Nodal Officer and inform the Proponent accordingly, regarding the Wildlife Clearance.
|
|
26
|
DFO (Jaintia Hills)
|
EDS
|
User Agency (piushillong@nhai.org)
|
27/04/2016
|
Please refer to the EDS raised by the Nodal Officer and inform the Proponent accordingly, regarding the Wildlife Clearance.
|
|
27
|
User Agency (piushillong@nhai.org)
|
REPLY
|
DFO (Jaintia Hills)
|
28/07/2016
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
28/07/2016
|
Sir, the U/A has been informed,correction has been done by them,
|
|
29
|
CF (Khasi&Jaintia Hills)
|
REPLY
|
Nodal Officer
|
29/08/2016
|
The Wildlife Clearance has been issued vide letter No. FWC/G/225/1192 dated 16 August 2016
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
09/09/2016
|
Wildlife clearance by Chief Wildlife Warden, Meghalaya communicated with Regional Office, MoEFCC,Shillong vide PCCF & HoFF's letter No.MFG.38/61 /Vol-I/5489 dtd 2.8.16. In-Principle Approval granted vide MoEFCC,Regional Office's letter F.No.3-MG B 049/ 2015-SHI 1873-74 dated 23.8.16.
|
|