Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Khasi Hills)
|
EDS
|
User Agency (sepheelectrical@gmail.com)
|
21/04/2022
|
Please submit undertaking for FRA certificate
|
|
2
|
User Agency (sepheelectrical@gmail.com)
|
REPLY
|
DFO (Khasi Hills)
|
21/04/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Khasi&Jaintia Hills)
|
23/06/2022
|
I am to inform you that in the online form of Part-II, the legal status of forest land proposed for diversion is mentioned as Reserved Forest and in the offline form of Part-II it is mentioned as Riat Laban RF and Laitkor PF.
In Part-III, the diverted land is mentioned as Laitkor RF. In this regard, you are requested to kindly clarify the legal status of the diverted forest land and give the break-up of the diverted area under PF and RF and also to resubmit the updated Part-II and Part-III and the updated KML file.
|
|
4
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Khasi Hills)
|
23/06/2022
|
I am to inform you that in the online form of Part-II, the legal status of forest land proposed for diversion is mentioned as Reserved Forest and in the offline form of Part-II it is mentioned as Riat Laban RF and Laitkor PF. In this regard, you are requested to kindly clarify the legal status of the diverted forest land and give the break-up of the diverted area under PF and RF and also to resubmit the updated Part-II and the updated KML file.
|
|
5
|
DFO (Khasi Hills)
|
EDS
|
User Agency (sepheelectrical@gmail.com)
|
24/06/2022
|
I am to inform you to that there are three forest land involved for the diversion of 0.11 ha, namely Law u Syiem Deemed Forest, Riat Laban Reserve Forest and Laitkor Protected Forest. In this regard, kindly submit a corrected GPS map and Updated KML file showing the area involved in each Forest land.
|
|
6
|
User Agency (sepheelectrical@gmail.com)
|
REPLY
|
DFO (Khasi Hills)
|
27/06/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Khasi Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
30/06/2022
|
Sir, I am to inform you that the Proposal of laying of pipeline passes through Laitkor Protected Forest (0.033 ha), Riat Laban Reserve Forest (0.023) ha and Law Syiem Deemed Forest (0.05 ha). Also, I have submitted the Part II online and updated the KML File.
|
|
8
|
CF (Khasi&Jaintia Hills)
|
REPLY
|
Nodal Officer
|
30/06/2022
|
Revised Part III has been uploaded as Eds Letter as per the EDS replies of DFO(T), Jowai and User Agency.
|
|