TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/ML/Others/26373/2017
(ii). Name of Project for which Forest Land is required :
RELIANCE JIO 4G Connectivity
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Laying of two numbers of HDPE Ducts of 40 mm Dia alond Road side berm at a depth 1.65 mtr below ground level . 2.Laying of 48 Fiber cable in one of the ducts .and 3 nos of NP2 manhole Chamber of 1200mm Height X 1000 mm Dia underground at 500mm
(iv). State :
Meghalaya
(v). Category of the Project :
Others
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Area of forest land proposed for diversion(in ha.):
0.2052
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/ML/Others/26373/2017
25/05/2017
29/05/2017
26/05/2017
29/05/2017
27/05/2017
30/05/2017
01/06/2017
Garo Hills
:
02/06/2017
Garo Hills
:
19/06/2017 (
Garo Hills
)
Meghalaya
:
06/07/2017
Meghalaya
:
10/07/2017
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
NOTE:-
Proposal is pending at
State Government
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
No Record Available
EDS History(Stage-II)
×