Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Garo Hills)
|
EDS
|
User Agency (eeirrigation.sgh@gmail.com)
|
09/07/2020
|
Please provide clear map indicating forest boundary. you have submitted blurred map, kindly provide clear map.
|
|
2
|
User Agency (eeirrigation.sgh@gmail.com)
|
REPLY
|
DFO (Garo Hills)
|
10/07/2020
|
The correction have been made as per the instruction received
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
25/04/2022
|
State Government is requested to provide clarification on the proposals.
|
|
4
|
State secretary
|
REPLY
|
Regional Office
|
25/05/2022
|
it is clarified that Sate Government has granted Stage I approval for diversion of 0.01 ha of forest land for hydrological station and it is same proposal showing pending with IRO Shillong. The State Govt. will withdraw the proposal
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
01/05/2023
|
State Govt vide letter dated 28.06.2022 has informed that this instant proposal have
already been approved Stage-I I II by the State Govt as per the letter dated 30.05.2022 enclosing the
Notification dated 23.04.2021. In this regard, the State Govt may kindly take up the matter with NIC,
New Delhi for necessary correction in the PARIVESH portal.
|
|