TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/TRANS/44469/2020              (ii). Name of Project for which Forest Land is required : Diversion of 3.064 ha. Forest land for Proposed 220 K.V. Umred to Ngbhid EHV Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : PROPOSAL OF 220 KV D/C TRANSMISSION LINE FROM EXISTING UMRED SUB STATION TO PROPOSSED NAGBHID SUB STATION UNDER MSETCL              (iv). File no. : FC-I/MH335/2023- NGP              (v). State : Maharashtra              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.064
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/TRANS/44469/202025/02/202028/02/2020   12/03/2020   13/03/2020   21/01/2021

Nagpur :27/01/2021


Bramhapuri :27/01/2021

Nagpur:
  11/11/2021 (Nagpur)

Chandrapur:
  12/02/2021 (Bramhapuri)

Maharashtra:
07/01/2022
Maharashtra:
20/10/2022
Nagpur:
18/12/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:10/01/2025  
Replied by State Government(Maharashtra) on:23/01/2025  
Query raised by State Government (Maharashtra) on:31/01/2023  
Replied by Nodal Officer (Maharashtra) on:05/12/2024  
Query raised by State Government (Maharashtra) on:17/01/2025  
Replied by Nodal Officer (Maharashtra) on:22/01/2025  
Query raised by Nodal Officer (Maharashtra) on:07/01/2022  
Replied by Circle(Nagpur) on:19/01/2022  
Query raised by Nodal Officer (Maharashtra) on:07/01/2022  
Replied by Circle(Chandrapur) on:08/02/2022  
Query raised by Nodal Officer (Maharashtra) on:02/03/2022  
Replied by Circle(Nagpur) on:29/03/2022  
Query raised by Nodal Officer (Maharashtra) on:02/03/2022  
Replied by Circle(Chandrapur) on:19/10/2022  
Query raised by Nodal Officer (Maharashtra) on:13/04/2023  
Replied by Circle(Nagpur) on:05/12/2023  
Query raised by Nodal Officer (Maharashtra) on:13/04/2023  
Replied by Circle(Chandrapur) on:06/12/2023  
Query raised by Nodal Officer (Maharashtra) on:07/12/2023  
Replied by Circle(Nagpur) on:14/02/2024  
Query raised by Nodal Officer (Maharashtra) on:07/12/2023  
Replied by Circle(Chandrapur) on:22/04/2024  
Query raised by Nodal Officer (Maharashtra) on:26/04/2024  
Replied by Circle(Chandrapur) on:11/11/2024  
Query raised by Nodal Officer (Maharashtra) on:26/04/2024  
Replied by Circle(Nagpur) on:27/11/2024  
Query raised by Nodal Officer (Maharashtra) on:17/01/2025  
Replied by Circle(Nagpur) on:20/01/2025  
Query raised by Nodal Officer (Maharashtra) on:17/01/2025  
Replied by Circle(Chandrapur) on:21/01/2025  
Query raised by Circle (Chandrapur) on:04/04/2022  
Replied by DFO (Bramhapuri) on:19/10/2022  
Query raised by Circle (Nagpur) on:18/04/2023  
Replied by DFO (Nagpur) on:05/12/2023  
Query raised by Circle (Nagpur) on:07/12/2023  
Replied by DFO (Nagpur) on:31/01/2024  
Query raised by Circle (Nagpur) on:29/04/2024  
Replied by DFO (Nagpur) on:14/11/2024  
Query raised by Circle (Nagpur) on:21/11/2024  
Replied by DFO (Nagpur) on:27/11/2024  
Query raised by Circle (Nagpur) on:20/01/2025  
Replied by DFO (Nagpur) on:20/01/2025  
Query raised by DFO (Bramhapuri) on:10/02/2021  
Replied by UA on :11/02/2021  
Query raised by DFO (Bramhapuri) on:06/04/2022  
Replied by UA on :30/05/2022  
Query raised by DFO (Nagpur) on:25/04/2023  
Replied by UA on :11/10/2023  
Query raised by DFO (Nagpur) on:16/05/2024  
Replied by UA on :16/10/2024  
Query raised by DFO (Nagpur) on:20/01/2025  
Replied by UA on :20/01/2025  
NOTE:- Proposal is pending at Regional Office .
Close(X)