TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/TRANS/27765/2017              (ii). Name of Project for which Forest Land is required : Laying of underground electric cable              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for diversion of 0.2289 ha forest land for laying of underground electric cable and construction of sub station (maintenance room)at Gharapuri island Tal Uran Dist raigad              (iv). File no. : FLD-1317/C.R.438/F-10              (v). State : Maharashtra              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.1772
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MH/TRANS/27765/201704/08/201705/08/2017   08/08/2017   11/08/2017   16/08/2017 Alibag :18/08/2017Thane:
  25/10/2017 (Alibag)

Maharashtra:
27/10/2017
Maharashtra:
29/12/2017
30/12/2017
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Alibag) on:19/08/2017  
Replied by UA on :25/09/2017  
Query raised by DFO (Alibag) on:05/10/2017  
Replied by UA on :06/10/2017  
NOTE:- Stage-I Approval accorded by : State Government .