  (i). Proposal No. : FP/MH/TRANS/20108/2016              (ii). Name of Project for which Forest Land is required : 765 kV D/C Warora - Parli Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : NTPC Limited (NTPC) is establishing coal based Gadarwara STPS of 2 X 800 MW generation project at Gadarwara, Narsinghpur District in Madya Pradesh. The Transmission System Strengthening is planned for the evacuation and supply of power from Gadarwara STPS to Maharashtra State.              (iv). File no. : FC-II/MH-65/2017-NGP              (v). State : Maharashtra              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 27.846
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/TRANS/20108/201621/06/2016aa27/06/2016   12/07/2016 Chandrapur :15/07/2016
Wardha :15/07/2016
Pandharkawada :15/07/2016
Yavatmal :15/07/2016
Pusad :15/07/2016
Nanded :15/07/2016
Hingoly :15/07/2016
Parbhani :15/07/2016
Pusad :15/07/2016
Beed :15/07/2016
Maharashtra:
30/06/2017
Maharashtra:
30/06/2017
Nagpur:
26/07/2017
02/09/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:18/08/2017  
Replied by State Government(Maharashtra) on:24/08/2017  
Query raised by DFO (Pusad) on:26/09/2016  
Replied by UA on :13/01/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .