  (i). Proposal No. : FP/MH/TRANS/13980/2015              (ii). Name of Project for which Forest Land is required : 132 KV Mokhabardi Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Maharashtra State Electricity Transmission Co. Ltd plan to construct and operate 132KV D/C Bhandara -Ambhora Transmission Line at Loc No. 182. This is to transmit bulk power from Bhandara (Sunflag) Sub Stn .to Mokhabardi Sub Stn. For Proposed Mokhabardi Lift Irrigation Scheme under Gosikhurd Project              (iv). State : Maharashtra              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 8.838
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/TRANS/13980/201517/07/201522/07/2015   22/07/2015   22/07/2015   23/07/2015 Pench(Wildlife Nagpur) :24/07/2015Wildlife Nagpur:
  15/12/2015 (Pench(Wildlife Nagpur))

Maharashtra:
15/12/2015
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Maharashtra) on:05/10/2021  
NOTE:- Proposal is pending at CF due to EDS raised by Nodal Officer .