Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Nanded)
|
EDS
|
User Agency (spnanded.ee@mahapwd.com)
|
18/01/2021
|
Please compliance As per dycf nanded letter
|
|
2
|
User Agency (spnanded.ee@mahapwd.com)
|
REPLY
|
DFO (Nanded)
|
23/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
15/02/2021
|
please correct fill up information in part no. II and resubmitted
|
|
4
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
15/02/2021
|
Part II of Proposal 5.34 ha is updated & correct information is submitted herewith
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
26/10/2021
|
as per Nodal Office request, it is being returned to Nodal Office
|
|
6
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
27/10/2021
|
Reminder issued by this office letter dt. 18/10/2021
|
|
7
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
27/10/2021
|
As per letter
|
|
8
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
28/10/2021
|
Query raised by this office letter dt. 04/08/2021
|
|
9
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
01/11/2021
|
Query raised by this office letter dt. 28/10/2021
|
|
10
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
29/11/2021
|
Submission of Information regarding said qurries
|
|
11
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
30/11/2021
|
Submit query compliance report
|
|
12
|
Nodal Officer
|
REPLY
|
State secretary
|
06/12/2021
|
Query compliance.
|
|