TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/45965/2020              (ii). Name of Project for which Forest Land is required : [AU-107] Construction of Two Lane Road with Paved Shoulders from Hadgaon – Tamsa – Bhokar – Umri – Karegaon – Lohgaon SH-251, Chainage 0/00 To 89/221 On Hybrid Annuity in Nanded District.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Government of Maharashtra has taken up a massive programme of up-gradation and development of existing two-lane State Highways. This stretch passes through Nanded district. The Nanded district is foremost players in tourism and aided industry along with agricultural. It is a need of an hour for              (iv). File no. : FC-II/MH-204/2022-NGP              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 7.62
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MH/ROAD/45965/202010/06/202016/06/2020   03/05/2022   04/05/2022   27/05/2022 Nanded :27/05/2022Aurangabad:
  12/08/2022 (Nanded)

Maharashtra:
14/09/2022
Maharashtra:
14/09/2022
Nagpur:
01/12/2022
31/01/2023
By :Regional Office
Maharashtra
20/06/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Aurangabad) on:24/08/2022  
Replied by DFO (Nanded) on:13/09/2022  
Query raised by DFO (Nanded) on:30/05/2022  
Replied by UA on :30/05/2022  
Query raised by DFO (Nanded) on:20/06/2022  
Replied by UA on :26/07/2022  
Query raised by DFO (Nanded) on:09/08/2022  
Replied by UA on :10/08/2022  
Query raised by DFO (Nanded) on:26/08/2022  
Replied by UA on :13/09/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Nagpur) on:30/06/2023  
Query raised by State Government (Maharashtra) on:04/08/2023  
Query raised by Nodal Officer on:07/08/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .