| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
State secretary
|
EDS
|
Nodal Officer
|
21/08/2022
|
provide the information sought by the State Government
|
|
|
2
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
22/08/2022
|
For query compliance
|
|
|
3
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
24/08/2022
|
For Query compliance
|
|
|
4
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
06/09/2022
|
Compliance for Quries 1 to 3 submission as per letter
|
|
|
5
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
13/09/2022
|
Back for query compliance
|
|
|
6
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
13/09/2022
|
Compliance for 1 to 3 Quries Submission as per letter
|
|
|
7
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
14/09/2022
|
Compliance submission against letter 1283 dt. 22-08-2022
|
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
15/09/2022
|
Query compliance
|
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
03/01/2023
|
Addl Info sought
|
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
03/01/2023
|
Provide the information and documents sought by the Regional Office
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
04/01/2023
|
For query compliance
|
|
|
12
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
07/01/2023
|
For query compliance
|
|
|
13
|
DFO (Nanded)
|
EDS
|
User Agency (naigaon.de@mahapwd.com)
|
09/01/2023
|
Compliance for 1 to 3 Quries
|
|
|
14
|
User Agency (naigaon.de@mahapwd.com)
|
REPLY
|
DFO (Nanded)
|
23/03/2023
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Nanded)
|
EDS
|
User Agency (naigaon.de@mahapwd.com)
|
24/03/2023
|
Letter issued to UA for Submit Revised information regarding 1 to 3 compliance as per IRO Nagpur
|
|
|
16
|
User Agency (naigaon.de@mahapwd.com)
|
REPLY
|
DFO (Nanded)
|
02/06/2023
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Nanded)
|
EDS
|
User Agency (naigaon.de@mahapwd.com)
|
16/06/2023
|
Quries information 1 to 3 has been sent to ccf Aurangabad
|
|
|
18
|
User Agency (naigaon.de@mahapwd.com)
|
REPLY
|
DFO (Nanded)
|
19/06/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
24/06/2023
|
this office vide letter No. No. Name/Land /FCA/280/23-24 dated 22/05/2023 Defect rectification report regarding points 1 to 3 has been submitted in 4 copies
|
|
|
20
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
28/06/2023
|
Compliance submission against letter NO. 2589 dt. 04-01-2023
|
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
30/06/2023
|
Query Compliance
|
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
08/08/2023
|
for further necessary action
|
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
02/04/2024
|
EDS
|
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
04/04/2024
|
EDS
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
04/04/2024
|
Query raised by this office letter Dated - 02/04/2024
|
|
|
26
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
19/12/2024
|
yes
|
|
|
27
|
DFO (Nanded)
|
EDS
|
User Agency (naigaon.de@mahapwd.com)
|
20/12/2024
|
Compliance for Quries 1 to 6 submission as per letter
|
|
|
28
|
User Agency (naigaon.de@mahapwd.com)
|
REPLY
|
DFO (Nanded)
|
24/12/2024
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
03/02/2025
|
Compliance for Quries
|
|
|
30
|
CF (Aurangabad)
|
EDS
|
DFO (Nanded)
|
23/06/2025
|
Compliance for Quries
|
|
|
31
|
DFO (Nanded)
|
EDS
|
User Agency (naigaon.de@mahapwd.com)
|
23/06/2025
|
Compliance for Quries
|
|
|
32
|
User Agency (naigaon.de@mahapwd.com)
|
REPLY
|
DFO (Nanded)
|
31/07/2025
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Nanded)
|
REPLY
|
CF (Aurangabad)
|
31/07/2025
|
Compliance for Quries
|
|
|
34
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
11/08/2025
|
Compliance for Quries
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
13/08/2025
|
For uploading documents
|
|
|
36
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
18/08/2025
|
compliance for Quires
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
19/08/2025
|
Query raised by this office letter Dated -19/08/2025
|
|
|
38
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
14/10/2025
|
compliance for Quires
|
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
20/10/2025
|
Query Compliance
|
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
30/10/2025
|
for further necessary action
|
|