Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Junnar)
|
EDS
|
User Agency (yuvarajpatil51@gmail.com)
|
24/06/2020
|
Proposal is not in complete form.
|
|
2
|
User Agency (yuvarajpatil51@gmail.com)
|
REPLY
|
DFO (Junnar)
|
14/08/2020
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Pune)
|
30/09/2021
|
query raised by this office letter dt. 05/07/2021
|
|
4
|
CF (Pune)
|
EDS
|
DFO (Junnar)
|
26/10/2021
|
For compliance
|
|
5
|
DFO (Junnar)
|
REPLY
|
CF (Pune)
|
01/11/2021
|
Desk-4.2/FCA-45/Land/45/2021-22, Dt. 26/10/2021
|
|
6
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
02/12/2021
|
Compliance submit
|
|
7
|
Nodal Officer
|
EDS
|
CF (Pune)
|
08/12/2021
|
Query raised by this office letter dt. 05/07/2021
|
|
8
|
CF (Pune)
|
EDS
|
DFO (Junnar)
|
04/02/2022
|
for compliance
|
|
9
|
DFO (Junnar)
|
EDS
|
User Agency (yuvarajpatil51@gmail.com)
|
16/02/2022
|
Proposal is incomplete
|
|
10
|
User Agency (yuvarajpatil51@gmail.com)
|
REPLY
|
DFO (Junnar)
|
09/04/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Junnar)
|
EDS
|
User Agency (yuvarajpatil51@gmail.com)
|
09/04/2022
|
Queries raised by APCCF Nodal
|
|
12
|
User Agency (yuvarajpatil51@gmail.com)
|
REPLY
|
DFO (Junnar)
|
19/04/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Junnar)
|
REPLY
|
CF (Pune)
|
19/05/2022
|
Complied
|
|
14
|
CF (Pune)
|
EDS
|
DFO (Junnar)
|
03/06/2022
|
for compliance
|
|
15
|
DFO (Junnar)
|
REPLY
|
CF (Pune)
|
10/06/2022
|
Complied.
|
|
16
|
CF (Pune)
|
EDS
|
DFO (Junnar)
|
13/06/2022
|
for compliance
|
|
17
|
DFO (Junnar)
|
REPLY
|
CF (Pune)
|
15/06/2022
|
Complied.
|
|
18
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
27/06/2022
|
compliance submitted
|
|