TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/39684/2019              (ii). Name of Project for which Forest Land is required : “Rehabilitation and Up-gradation of Shahpur Patgaon Section 1 &2 – (KM 0+000 to KM 20+130) and (KM 20+130 to KM 43+600) part of NH-3 Shahpur - Murbad – Mhasa – Karjat - Khopoli-NH4 section of newly              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed Project is starting from existing KM 0+000 to 20+130. The approximate length of Project is 20.130 KM, It passes through one district of Maharashtra, Thane. The villages falling on the alignment are Gotheghar, Kaambare, Waamde, Saapgaon, Khutghar, Nandgaon, Lenaadkhurd, Shendroon budruk              (iv). File no. : FC-II/MH-150/2021-NGP              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 17.01
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MH/ROAD/39684/201902/04/201908/05/2019  03/04/2019   24/05/2019  06/05/2019   31/05/2019   30/07/2019 Shahapur :06/08/2019Thane:
  27/07/2020 (Shahapur)

Maharashtra:
25/08/2020
Maharashtra:
29/10/2020
Nagpur:
10/03/2021
30/06/2021
By :Regional Office
Maharashtra
05/08/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:30/04/2021  
Replied by State Government(Maharashtra) on:25/10/2021  
Query raised by State Government (Maharashtra) on:07/05/2021  
Replied by Nodal Officer (Maharashtra) on:04/06/2021  
Query raised by Nodal Officer (Maharashtra) on:18/05/2021  
Replied by Circle(Thane) on:19/05/2021  
Query raised by Circle (Thane) on:18/05/2021  
Replied by DFO (Shahapur) on:18/05/2021  
Query raised by DFO (Shahapur) on:01/07/2020  
Replied by UA on :02/07/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Nagpur) on:26/09/2022  
Query raised by State Government (Maharashtra) on:30/09/2022  
Query raised by Nodal Officer on:03/10/2022  
Replied by UA on :28/02/2023  
Query raised by Nodal Officer on:03/05/2023  
Replied by UA on :31/03/2025  
Query raised by Nodal Officer on:08/04/2025  
Replied by UA on :30/04/2025  
Query raised by Nodal Officer on:02/05/2025  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .