Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Amravati)
|
EDS
|
DFO (Buldhana)
|
22/11/2017
|
Query raised by APCCF Nodal,office on 12 points
|
|
2
|
DFO (Buldhana)
|
EDS
|
User Agency (msrdcmumbaipune@gmail.com)
|
02/12/2017
|
Difference in area, Quarry raised by APCCF, Nodal same has been conveyed by CCF Amravati
|
|
3
|
User Agency (msrdcmumbaipune@gmail.com)
|
REPLY
|
DFO (Buldhana)
|
02/12/2017
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Buldhana)
|
REPLY
|
CF (Amravati)
|
29/12/2017
|
all compliance submitted
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
11/06/2018
|
addl info sought
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
11/07/2018
|
Letter dt.07/06/2018 is attached herewith for ready reference. Please submit the query compliance report to MOEF&CC, RO, Nagpur at the earlist.
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
19/07/2018
|
EDS REPLY SUBMITTED HEREWITH
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
19/07/2018
|
Nodal Office submitted EDS reply vide letter dt. 19/07/2018
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
05/09/2018
|
addl info sought
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
15/10/2018
|
Nodal Office submitted their EDS reply on 05/10/2018 which is attached herewith.
|
|