TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/17303/2015              (ii). Name of Project for which Forest Land is required : Construction of link road between Thane Belapur Road to NH 4 including Tunnel through Parsik Hill in Taluka & District Thane              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for obtaining approval of MoEF & CC, Govt. of India for construction of of Link road between Thane Belapur Road to National Highway No.4 Pune Road including Tunnel through Parsik Hill in Taluka & Dist.Thane. This corridor would provide direct transport connectivity to the existing built up              (iv). File no. : FC-IIMH-76-2018-NGP              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 18.1824
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/ROAD/17303/201501/01/2016aa04/01/2016   08/01/2016 Thane :12/01/2016Thane:
  04/10/2017 (Thane)

Maharashtra:
11/10/2017
Maharashtra:
28/12/2017
Nagpur:
10/01/2018
26/03/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:14/02/2018  
Replied by State Government(Maharashtra) on:15/03/2018  
Query raised by Nodal Officer (Maharashtra) on:19/12/2017  
Replied by Circle(Thane) on:20/12/2017  
Query raised by Circle (Thane) on:19/12/2017  
Replied by DFO (Thane) on:20/12/2017  
Query raised by DFO (Thane) on:19/12/2017  
Replied by UA on :20/12/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .