Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Pune)
|
19/08/2022
|
For query compliance
|
|
2
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
22/08/2022
|
for compliance
|
|
3
|
DFO (Pune)
|
EDS
|
User Agency (eenorth_zppune@enviroconcern.in)
|
13/09/2022
|
For Compliance
|
|
4
|
User Agency (eenorth_zppune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
27/09/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
09/10/2022
|
Compliance report by this office lettr no A 217 Dt 07.10.2022
|
|
6
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
14/11/2022
|
quarry compliance submitted
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
13/01/2023
|
Additional Info Sought
|
|
8
|
Nodal Officer
|
EDS
|
CF (Pune)
|
16/01/2023
|
For query compliance
|
|
9
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
17/01/2023
|
for compliance
|
|
10
|
DFO (Pune)
|
EDS
|
User Agency (eenorth_zppune@enviroconcern.in)
|
20/01/2023
|
state govt of maharastra letter dt.13.01.2023 and apccf nodal letter no.2695 dt.16.01.2023 query compliance required.
|
|
11
|
User Agency (eenorth_zppune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
07/02/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
08/02/2023
|
Query reply this office letter no 649, dt.07.02.2023.
|
|
13
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
14/02/2023
|
query compliance
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
14/02/2023
|
Query compliance
|
|