TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/154545/2022              (ii). Name of Project for which Forest Land is required : Proposal for diversion of 8.4771 Ha of forest land for up-gradation and widening of Mudkhed-Bhokar NH-161A section from km 22.000 to Km. 43.000 of 21 km length in Mudkhed & Bhokar Talukas, Nanded Dist              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Mudkhed-Bhokar Road National Highway-161A section from km 22.000 to 43.000 is currently a 3.75 m wide road. The road to Bhokar is in bad condition at present. Since Bhokar is close to the Telangana border, the area observes heavy traffic for Nirmal, Mhesa, Adilabad and Kinwat. This traffic is obstru              (iv). File no. : FC-II/MH-196/2022-NGP              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.4771
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MH/ROAD/154545/202217/04/2022aa18/04/2022   26/05/2022 Nanded :26/05/2022Aurangabad:
  28/05/2022 (Nanded)

Maharashtra:
02/06/2022
Maharashtra:
22/06/2022
Nagpur:
16/09/2022
30/05/2023
By :Regional Office
Maharashtra
05/10/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:25/10/2022  
Replied by State Government(Maharashtra) on:12/12/2022  
Query raised by State Government (Maharashtra) on:27/10/2022  
Replied by Nodal Officer (Maharashtra) on:07/12/2022  
Query raised by Nodal Officer (Maharashtra) on:28/10/2022  
Replied by Circle(Aurangabad) on:05/12/2022  
Query raised by Circle (Aurangabad) on:01/11/2022  
Replied by DFO (Nanded) on:22/11/2022  
Query raised by DFO (Nanded) on:07/11/2022  
Replied by UA on :21/11/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Nagpur) on:16/10/2023  
Query raised by State Government (Maharashtra) on:17/10/2023  
Query raised by Nodal Officer on:17/10/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .
Close(X)