TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/148243/2021              (ii). Name of Project for which Forest Land is required : Diversion of forest land for improvement of existing road MDr 124,Road fromNH 54,Rui, Saval, Bhadalwadi, Dalaj no 2, Kumbhargaon Tal. Indapur,Dist. Pune. ,              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of forest land for improvement of existing road MDr 124,Road fromNH 54,Rui, Saval, Bhadalwadi, Dalaj no 2, Kumbhargaon Tal. Indapur,Dist. Pune.Road passing through Forest land, at Bhadalwadi, Kumbhargaon, Tal.-Indapur,Dist.-Pune              (iv). File no. : FLD-2022/CR-157/F-10              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.6256
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MH/ROAD/148243/202125/10/202125/10/2021   25/10/2021   27/10/2021   29/11/2021 Pune :30/11/2021Pune:
  07/03/2022 (Pune)

Maharashtra:
12/04/2022
Maharashtra:
18/05/2022
26/07/2022
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Maharashtra) on:27/01/2023  
Replied by Nodal Officer (Maharashtra) on:31/01/2023  
Query raised by DFO (Pune) on:28/12/2021  
Replied by UA on :07/03/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
   Query raised by State Government (Maharashtra) on:25/08/2023  
Query raised by Nodal Officer on:28/08/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government for verifying Compliance of Conditions .