Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Pune)
|
02/03/2022
|
Query raised by this office letter dt 14-01-22.
|
|
2
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
25/05/2022
|
compliance summited
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
22/12/2022
|
Addl Info Sought
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
26/12/2022
|
Submit one more physical copy of entire proposal so that it can be forwarded to MoEF&CC, New Delhi
|
|
5
|
Nodal Officer
|
REPLY
|
State secretary
|
29/12/2022
|
for necessary action
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
29/12/2022
|
Govt. of Maharashtra has submitted a physical copy of proposal to Regional Office, Nagpur. Regional Office has conveyed that proposal should be dealt at Ministry Level. State Govt. dont have extra set of proposal for MoEF&CC, Head Office. Therefore, submit the physical copy of a proposal to State Govt. through special messenger at the earliest. After receipt of physical copy proposal can be submitted to MoEF&CC, Head Office at Delhi
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
10/01/2023
|
Query Compliance
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
27/01/2023
|
As per IRO, MoEF&CC, Nagpur instructions Physical Copy of this proposal is forwarded to MoEF&CC, Delhi but Government of Maharashtra is unable to send it to MoEF&CC, Delhi office as system by default sends it to your office due to required forest land is below 40 ha. and project is linear in nature.
Therefore, IRO, MoEF&CC, Nagpur is requested to forward this proposal to Head Office of MoEF&CC at New Delhi on PARIVESH portal.
|
|
9
|
Head Office
|
EDS
|
State secretary
|
07/08/2023
|
EDS
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
10/08/2023
|
Addl Info Sought
|
|
11
|
Nodal Officer
|
EDS
|
CF (Pune)
|
11/08/2023
|
Query raised by this office letter Dated - 10/08/2023
|
|
12
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
11/08/2023
|
query
|
|
13
|
DFO (Pune)
|
EDS
|
User Agency (to_ardepune@enviroconcern.in)
|
17/08/2023
|
comlpiace as per apccf & nodal offficer letter dt.10.08.2023
|
|
14
|
User Agency (to_ardepune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
21/03/2024
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
03/04/2024
|
query compliance
|
|
16
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
06/05/2024
|
Query Compliance Done
|
|
17
|
Nodal Officer
|
EDS
|
CF (Pune)
|
16/05/2024
|
Query raised by this office letter Dated -15/05/2024
|
|
18
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
21/05/2024
|
query raised
|
|
19
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
18/06/2024
|
query compliance as per apccf & nodal sir letter dt.15.05.2024
|
|
20
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
27/06/2024
|
Query Compliance Done Letter No. d-4/land/FCA 339 /2024.25 /A 333 Dt. 19/06/2024
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
28/06/2024
|
Query Compliance
|
|
22
|
State secretary
|
REPLY
|
Head Office
|
03/07/2024
|
for necessary action
|
|
23
|
Head Office
|
EDS
|
State secretary
|
19/08/2024
|
EDS
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
28/08/2024
|
Addl Info Sought by GoI
|
|
25
|
Nodal Officer
|
EDS
|
CF (Pune)
|
28/08/2024
|
Query raised by this office letter Dated - 20/8/2024
|
|
26
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
29/08/2024
|
Query raised letter no. 1340 Dt. 22/08/2024
|
|
27
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
22/04/2025
|
query compliance
|
|
28
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
22/04/2025
|
Quarry Compliance done
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
23/04/2025
|
Query compliance
|
|
30
|
State secretary
|
REPLY
|
Head Office
|
23/04/2025
|
For further necessary action
|
|