TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/142578/2021              (ii). Name of Project for which Forest Land is required : The construction of widening,strengthening, tarring and upgrading existing four lane Pune-Shirur-Ahmednagar road in to six lane is to be passing through reserved forest land Comptt. No. 303 Gat No.673, 674 and Gat No.678 of village-Koregaonbhima Tal-Shirur District-Pune. The Government of Maharashtra has taken the initiative of improvement and wid              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The construction of widening,strengthening, tarring and upgrading existing four lane Pune-Shirur-Ahmednagar road in to six lane is to be passing through reserved forest land Comptt. No. 303 Gat No.673, 674 and Gat No.678 of village-Koregaonbhima Tal-Shirur District-Pune. The Government of Maharas              (iv). File no. : FLD-1923/C.R.43/F-10              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.9675
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MH/ROAD/142578/202125/05/202104/06/2021   09/06/2021   17/06/2021   04/08/2021 Junnar :30/09/2021Pune:
  23/09/2022 (Junnar)

Maharashtra:
05/12/2022
Maharashtra:
12/01/2023
20/03/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Pune) on:15/11/2022  
Replied by DFO (Junnar) on:23/11/2022  
Query raised by DFO (Junnar) on:19/10/2021  
Replied by UA on :10/01/2022  
Query raised by DFO (Junnar) on:19/01/2022  
Replied by UA on :25/08/2022  
Query raised by DFO (Junnar) on:12/09/2022  
Replied by UA on :14/09/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
   Query raised by State Government (Maharashtra) on:09/08/2024  
Replied by Nodal Officer (Maharashtra) on:12/08/2024  
Query raised by State Government (Maharashtra) on:10/02/2025  
Query raised by Nodal Officer on:12/02/2025  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government for verifying Compliance of Conditions .