TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/REHAB/144503/2021              (ii). Name of Project for which Forest Land is required : Rehabilitation of Village Vele from Koyana Wildlife Sanctuary i.e. core area of Sahyadri Tiger Reserve.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for Diversion of 112.25 ha. Reserve Forest land of Village – Manecoloy Gat no 250, Dhangawadi Gat no. 389, Bholi Gat no. 362, 363 Tal. Khandala, Dist. Satara for rehabilitation of Vele village from Koyana Wildlife Sanctuary i.e. from Core of Sahyadri Tiger Reserve.              (iv). File no. : 8-07/2022-FC              (v). State : Maharashtra              (vi). Category of the Project : Rehabilitation              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 112.25
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MH/REHAB/144503/202107/07/2021aa14/07/2021   14/07/2021 Satara :14/07/2021Kolhapur:
  15/07/2021 (Satara)

Maharashtra:
14/10/2021
Maharashtra:
15/03/2022
12/05/202217/10/2022
11/01/2023
06/03/2023
By :Head Office
Maharashtra
26/05/2023
29/01/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 01/06/2022  
Replied by State Government (Maharashtra) on:16/09/2022  
Query raised by State Government (Maharashtra) on:02/06/2022  
Replied by Nodal Officer (Maharashtra) on:22/08/2022  
Query raised by Nodal Officer (Maharashtra) on:01/11/2021  
Replied by Circle(Kolhapur) on:26/11/2021  
Query raised by Nodal Officer (Maharashtra) on:03/06/2022  
Replied by Circle(Kolhapur) on:10/08/2022  
Query raised by Circle (Kolhapur) on:04/08/2021  
Replied by DFO (Satara) on:24/08/2021  
Query raised by Circle (Kolhapur) on:21/09/2021  
Replied by DFO (Satara) on:29/09/2021  
Query raised by Circle (Kolhapur) on:13/10/2021  
Replied by DFO (Satara) on:13/10/2021  
Query raised by Circle (Kolhapur) on:08/11/2021  
Replied by DFO (Satara) on:12/11/2021  
Query raised by Circle (Kolhapur) on:09/06/2022  
Replied by DFO (Satara) on:09/07/2022  
Query raised by DFO (Satara) on:14/07/2021  
Replied by UA on :14/07/2021  
Query raised by DFO (Satara) on:06/07/2022  
Replied by UA on :09/07/2022  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 20/06/2023  
Replied by State Government (Maharashtra) on:30/08/2023  
Query raised by MoEFCC,New Delhi 01/09/2023  
Replied by State Government (Maharashtra) on:15/12/2023  
Query raised by State Government (Maharashtra) on:01/08/2023  
Replied by Nodal Officer (Maharashtra) on:18/08/2023  
Query raised by State Government (Maharashtra) on:04/09/2023  
Replied by Nodal Officer (Maharashtra) on:15/12/2023  
Query raised by Nodal Officer on:03/08/2023  
Replied by UA on :17/08/2023  
Query raised by Nodal Officer on:06/09/2023  
Replied by UA on :14/12/2023  
NOTE:- Stage-II Approval accorded by : Head Office .