| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
25/08/2022
|
Complaince For 1 to 15 back query revise submission proposal
|
|
|
2
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
08/10/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
12/10/2022
|
The following errors have again been found in the submitted proposal.
|
|
|
4
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
20/10/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
20/10/2022
|
Complaince For 1 to 9 back query revise submission proposal
And Submit finalized JMS data alonwith maps and area statement.
|
|
|
6
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
26/11/2022
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
01/12/2022
|
Please submit gut no and sy no detail in proposed railway line
|
|
|
8
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
04/12/2022
|
Complaince For 1 to 6 back query revise submission proposal And Submit finalized JMS data alonwith maps and area statement.
|
|
|
9
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
08/12/2022
|
The correction have been made as per the instruction received
|
|
|
10
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
08/12/2022
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
12/12/2022
|
The users agency reply dated 08/12/2022 in PARIVESH portal regarding back query revise proposal, but revise proposal hard copy or soft copy is not yet received in this office from user agency.
|
|
|
12
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
16/12/2022
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
18/12/2022
|
Complaince For 1 to 5 back query revise submission proposal And Submit finalized JMS data alongwith maps and area statement.
|
|
|
14
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
03/01/2023
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
09/01/2023
|
Proposal not yet submitted
|
|
|
16
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
12/01/2023
|
On received proposal was scrutinized, 1 to 13 query have been found in it, please compliance and submit revised proposal again.
|
|
|
17
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
23/01/2023
|
The correction have been made as per the instruction received
|
|
|
18
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
23/01/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
25/01/2023
|
Kindly update KML file.
|
|
|
20
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
25/01/2023
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
06/02/2023
|
Proposal not yet submitted by user agency
|
|
|
22
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
08/02/2023
|
During the inspection of the affected area in Gut No.44 of Mauje Tuljapur Tal. Tuljapur, it appears that the reserve forest area affected is 1.00 hectors, please confirm the remaining area and resubmit the proposal.
|
|
|
23
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
06/03/2023
|
The correction have been made as per the instruction received
|
|
|
24
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
06/03/2023
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
06/03/2023
|
Proposal not yet submitted by user agency
|
|
|
26
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
02/04/2023
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
03/04/2023
|
Proposal not yet submitted by user agency
|
|
|
28
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
28/04/2023
|
Railway proposal in Five Hard copies and CDs were forwarded to Office of the Deputy Conservator of Forest, Forest Division, Solapur for further necessary action.
|
|
|
29
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
14/05/2023
|
The correction have been made as per the instruction received
|
|
|
30
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
14/05/2023
|
The correction have been made as per the instruction received
|
|
|
31
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
30/05/2023
|
quarry compliance of this office letter dt 29 05 2023
|
|
|
32
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
14/06/2023
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
16/06/2023
|
Compliance not properly done please submit correct comply report
|
|
|
34
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
05/07/2023
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
10/07/2023
|
Quarry compliance of this office letter dt 06 07 2023
|
|
|
36
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
10/07/2023
|
The correction have been made as per the instruction received
|
|
|
37
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
14/07/2023
|
We are awaiting response from DCF Wildlife Pune regarding require or not require Wildlife clearance as some of the gut nos are part of ESZ of GIB sanctuary
|
|
|
38
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
26/07/2023
|
The correction have been made as per the instruction received
|
|
|
39
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
11/09/2023
|
Please submit Hard copy of proposal in 7 sets
|
|
|
40
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
16/09/2023
|
The correction have been made as per the instruction received
|
|
|
41
|
Nodal Officer
|
EDS
|
CF (Aurangabad)
|
21/11/2023
|
Query Raised by this office letter Dated -20/11/2023
|
|
|
42
|
Nodal Officer
|
EDS
|
CF (Pune)
|
21/11/2023
|
Query Raised by this office letter Dated -20/11/2023
|
|
|
43
|
CF (Pune)
|
EDS
|
DFO (Solapur)
|
10/01/2024
|
query
|
|
|
44
|
DFO (Solapur)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
19/01/2024
|
Please submit back quarry compliance
|
|
|
45
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Solapur)
|
21/02/2024
|
The correction have been made as per the instruction received
|
|
|
46
|
DFO (Solapur)
|
REPLY
|
CF (Pune)
|
22/02/2024
|
Query compliance done
|
|
|
47
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
14/03/2024
|
query compliance
|
|
|
48
|
CF (Aurangabad)
|
EDS
|
DFO (Osmanabad)
|
05/11/2024
|
Please check for further action.
|
|
|
49
|
DFO (Osmanabad)
|
EDS
|
User Agency (dycebhusawal2022@gmail.com)
|
05/11/2024
|
The user agency should submit the complete documents regarding compensatory afforestation to this office immediately.
|
|
|
50
|
User Agency (dycebhusawal2022@gmail.com)
|
REPLY
|
DFO (Osmanabad)
|
11/12/2024
|
The correction have been made as per the instruction received
|
|
|
51
|
DFO (Osmanabad)
|
REPLY
|
CF (Aurangabad)
|
11/12/2024
|
Query Compliance by DFO office
|
|
|
52
|
CF (Aurangabad)
|
EDS
|
DFO (Osmanabad)
|
16/12/2024
|
submit for Necessary action
|
|
|
53
|
DFO (Osmanabad)
|
REPLY
|
CF (Aurangabad)
|
16/12/2024
|
compliance submitted
|
|
|
54
|
CF (Aurangabad)
|
REPLY
|
Nodal Officer
|
16/12/2024
|
Compliance submitted
|
|