TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/Pipeline/48180/2020              (ii). Name of Project for which Forest Land is required : : Proposal for Ex- post Facto Approval for Diversion of Forest Land for Laying Water Intake Pipeline for BGPPL, Bhigwan, Tehsil Indapur, District Pune              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : A 7.465 Km long pipeline, partially underground and partially overground was laid in 1996-97 to carry water from Ujani Back Waters to BGPPL, Bhigwan unit. Out of which, 5.533km traverse through the Forest Land, without obtaining Forest Clearance. Hence, the proposal is submitted for seeking ex- post              (iv). State : Maharashtra              (v). Category of the Project : Pipeline              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.83
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/Pipeline/48180/202024/09/202028/09/2020   30/09/2020   01/10/2020   29/03/2021 Pune :10/05/2021Pune:
  08/12/2022 (Pune)

Maharashtra:
26/12/2022
Maharashtra:
02/02/2023
Nagpur:
08/11/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:05/01/2024  
Replied by State Government(Maharashtra) on:28/03/2025  
Query raised by Regional Office (Nagpur) on:29/03/2025  
Replied by State Government(Maharashtra) on:03/04/2025  
Query raised by State Government (Maharashtra) on:16/05/2023  
Replied by Nodal Officer (Maharashtra) on:28/07/2023  
Query raised by State Government (Maharashtra) on:19/01/2024  
Replied by Nodal Officer (Maharashtra) on:23/01/2024  
Query raised by State Government (Maharashtra) on:21/02/2024  
Replied by Nodal Officer (Maharashtra) on:13/03/2024  
Query raised by Nodal Officer (Maharashtra) on:30/12/2022  
Replied by Circle(Pune) on:24/01/2023  
Query raised by Nodal Officer (Maharashtra) on:31/01/2023  
Replied by Circle(Pune) on:02/02/2023  
Query raised by Nodal Officer (Maharashtra) on:16/05/2023  
Replied by Circle(Pune) on:28/07/2023  
Query raised by Circle (Pune) on:03/01/2023  
Replied by DFO (Pune) on:24/01/2023  
Query raised by Circle (Pune) on:16/05/2023  
Replied by DFO (Pune) on:13/07/2023  
Query raised by DFO (Pune) on:11/05/2021  
Replied by UA on :12/05/2021  
Query raised by DFO (Pune) on:02/02/2022  
Replied by UA on :12/08/2022  
Query raised by DFO (Pune) on:30/11/2022  
Replied by UA on :06/12/2022  
Query raised by DFO (Pune) on:20/06/2023  
Replied by UA on :13/07/2023  
NOTE:- Proposal is pending at Regional Office .